Cripple Creek&Victor Gold Mining Company <br /> Squaw Gulch VLF Phase 2A Part 1 ■ <br /> Record of Construction Report <br /> 475.0106.032 <br /> July 22,2019 <br /> CAT 730 Haul Trucks Edge TRT622 Trommel <br /> Volvo A30 Haul Truck Tandem Axle Water Trucks <br /> CAT 740 Haul Trucks CAT 740 Water Truck <br /> CAT 777 Haul Trucks CAT 773 Water Wagon <br /> 2.1. Clearing and Grubbing <br /> The footprint of the Phase 2A Part 1 Squaw Gulch VLF was stripped of all deleterious materials. <br /> Any soil containing vegetation was removed and placed in several site topsoil stockpiles <br /> designated by CC&V. All cleared areas were inspected by the CQA Monitor to ensure that all <br /> deleterious material was removed prior to further construction activities. <br /> 2.2. Underground Working Remediation <br /> Historic underground workings within the Squaw Gulch VLF Phase 2 footprint were remediated <br /> in accordance with IFC Drawing A38 and the project Technical Specifications. IFC Drawings, A30 <br /> through A38, present all historic underground workings that were known at the start of <br /> construction. All underground workings that were encountered within the Phase 2 limits during <br /> construction were given a unique identification number and are summarized in the table <br /> presented in Appendix D.1. The table includes the historic identification number, identification <br /> number, location (northing, easting, and surface elevation), type of working, remediation type, <br /> remediation quantities and remarks regarding the remediation. Workings were only identified if <br /> they were within 50 feet of the finished subgrade surface. Investigation and remediation was <br /> not required for any workings that exist at a depth greater than 50 feet below the finished <br /> subgrade surface. Appendix D.2 contains a layout of all underground workings that were <br /> remediated within the Phase 2 limits. <br /> 2.2.1. Confirmatory Drilling <br /> Confirmatory drilling was performed at all workings that were known or encountered <br /> during Phase 2 construction in order to help define the limits of the working. The goal of <br /> the confirmatory drilling was to isolate the working so that the proper remediation <br /> could be completed. <br /> Pneumatic hammer track drill rigs were used to drill three-inch diameter holes, on a 4- <br /> foot grid, to a depth of 50 feet from the pad finished grade elevation. If drilling activities <br /> indicated that 50 feet of crown pillar existed above the working, then the drill hole was <br /> marked as a "miss." If any voids were encountered during drilling, then the drill hole <br /> was marked as a "hit," and the void depths were recorded. After the working was <br /> encompassed by "misses," a remediation plan was developed for the working. <br /> P.\Projects\0106.032 VLF2 Phase 2 CQA\J-REPORTS\ROC Report 1\Cert Report-Phase 2A Part 1\475.0106.032 CCV PHASE 2A Part 1 <br /> ROC REPORT.docx <br /> Page 2 <br />