Laserfiche WebLink
G <br /> 1� COLORADO LEGACY LAND <br /> Schedule for Implementation: <br /> The NWRP diversion pipeline project is expected to be completed in 2019. The attached Gantt chart presented <br /> the construction schedule and milestones for the project. This project includes four phases: <br /> 1. January to May 2019-Engineering Design and Preparation <br /> 2. May to June 2019-Regulatory Review,Response and Approval <br /> 3. June to August 2019-Mobilization and Procurement <br /> 4. August to September 2019-Construction <br /> If you have any questions regarding this technical revision,please don't hesitate to contact me. Sincerely, <br /> Jim Harrington,Managing Director <br /> COLORADO LEGACY LAND <br /> JimPColoradoLegacv Land <br /> cc: Paul Newman-CLL,Managing Director,paul@coloradolegacy.land <br /> Eric Williams-CLL,Managing Director,eric r c�,l��r�xl��ley.land <br /> Billy Ray-Alexco Water&Environment Inc,Project Manager,gray@alexcoresource.com <br />