2. Mining Timetable <br /> The following timetable is a best estimate of the sequence of operations for the life of the mine <br /> after May 2019 and is based on mining and selling 200,000 tons of total product per year: <br /> Table D-1 Mining Timetable <br /> Area Mining Time Material Quantity <br /> 1 3.9 Years 780,000 Tons <br /> 2 3.3 Years 660,000 Tons <br /> 3 3.6 Years 720,000 Tons <br /> 4 5.2 Years 1,030,000 Tons <br /> 5 4.9 Years 970,000 Tons <br /> West Pit Subtotal 20.8 Years 4,160,000 Tons <br /> 6 2.7 Years 540,000 Tons <br /> 7 5.1 Years 1,030,000 Tons <br /> 8 6.4 Years 1,270,000 Tons <br /> 9 7.1 Years 1,430,000 Tons <br /> 10 8.3 Years 1,670,000 Tons <br /> East Pit Subtotal 29.7 Years 5,930,000 Tons <br /> Total 50.5 Years 10,090,000 Tons <br /> The mining schedule is planned to minimize disturbance by reclaiming areas as additional <br /> mining is undertaken. If large contracts are awarded to the site, production could increase, <br /> thereby curtailing the life of the pit. On the other hand, if contracts are less than anticipated, the <br /> life of the pit could be extended. This table is based on a reasonable projection of production <br /> rates. <br /> 3. Mine Facilities and Operation <br /> The site will contain the following facilities; it is noted where applicable whether or not the facility <br /> is portable and whether it will have any fuel storage associated with it. A summary of equipment <br /> and related tanks is shown below. <br /> - A portable asphalt plant with associated tanks <br /> - A concrete plant with associated tanks <br /> BRS&G hit 1 l.n�I eHi Ai anA \stoci.ur.,I'I I i <br /> March 2019 D-4 <br />