Laserfiche WebLink
L.G. EVERIST, INC. FIRESTONE GRAVEL RESOURCE <br /> M-1996-052 Revised: January 31, 2019 <br /> Mining Timetable(REVISED JANUARY 2019) <br /> The continuing uncertainty of economic conditions in the <br /> construction materials industry precludes an accurate forecast of <br /> demand for materials during the life of the mine. We therefore, <br /> can only estimate the mining timetable based on an average year <br /> and may expect a specific year to vary widely from the average. <br /> M NING TIMETABLE <br /> ACRES ± <br /> AREA* YEARS <br /> TOTAL MINED MISC (I.E. <br /> AREA SETBACKS <br /> AND <br /> UNDISTURBED <br /> , ETC. ) <br /> Area 1 1-2 12.49 9.31 3 .18 <br /> Area 2 2-4 34.89 28.49 5.13 <br /> Area 3 12-14 120.68 112.05 7.64 <br /> Area 4 1-3 18.07 14 .97 2.81 <br /> Area 5 15-17 156.66 144 .50 8.63 <br /> TOTALS 31-40 342 .79 309.32 27.39 <br /> * areas are only used to explain the mining areas,not the direction or timing of <br /> the mining operations. <br />