Laserfiche WebLink
■NewFields <br /> IPerspective.Vision. Solutions. <br /> FIELD DAILY PROGRESS REPORT <br /> Client: Cripple Creek&Victor Gold Mining Company <br /> Project: VLF2 Geomembrane Recertification <br /> ' NewFields Project Number:475.0106.026 <br /> Date: April 10, 2018 <br /> S M T W T F S <br /> Temperature: Low: 33°F to High: 59°F Weather: Partly Cloudy <br /> NEWFIELDS PERSONNEL <br /> Name Hours <br /> Benjamin Melly 10 <br /> 1.0 AMES CONSTRUCTION ACTIVITIES <br /> ' 1.1 Ore Excavation <br /> A CAT D9T dozer and a CAT D6T LGP dozer assisted by a CAT 330B excavator removed ore material <br /> ' between the 9750' and 98S0' benches stockpiling near 9750' bench. The D6T and 330E worked <br /> on a minimum of 2' of geomembrane cover and the D9T worked on a minimum of 4' of <br /> ' geomembrane cover. <br /> An eight-inch CPe pipe was exposed using a mini excavator and laborers. The pipe was cut to <br /> allow the fish tape to be placed in the pipe. The fish tape was pushed down the slope in the pipe. <br /> The fish tape stopped and was measured at 82' which is most likely the bend of the pipe at the <br /> crest of 9750 bench. <br /> The mini excavator was utilized to excavate test pits to locate the geomembrane along the 9778' <br /> ' elevation. Five test pits were excavated at an interval of twenty feet. <br /> 1.2 Geomembrane Installation: <br /> ' No activities performed during the shift. <br />