Daily Report ■ <br /> VLF2 Geomembrane Recertification <br /> 475.0106.026 ■ <br /> July 7,2018 <br /> 2.2 Geomembrane Installation <br /> Approximately 22,275 square feet (Panels PRC-33 to PRC-41) of 80 Mil LLPDE double sided <br /> textured geomembrane was installed by Comanco during the shift.Approximately 945 linear feet <br /> of fusion seaming was performed using one fusion machine/operator combination. One <br /> destructive testing sample was marked during fusion seaming. Non-destructive testing was <br /> performed for fusion welded seams. No repairs were performed during the shift. Comanco used <br /> the sandbags to secure geomembrane in place. <br /> 3.0 NEWFIELDS ACTIVITIES <br /> NewFields personnel observed DCF placement, anchor trench backfill, and geomembrane <br /> installation during the shift. <br /> 4.0 COMMUNICATIONS AND MEETINGS <br /> NewFields personnel attended a project pre-shift safety meeting conducted by Ames <br /> Construction. <br /> If you have any questions or require additional information, please contact us at your <br /> convenience. <br /> Sincerely, <br /> NewFields Mining Design &Technical Services <br /> Prepared by: Benjamin Melly. 817.889.7315 <br />