PERMIT#: M-2018-011 <br /> INSPECTOR'S INITIALS: ECS <br /> INSPECTION DATE: September 6,2018 <br /> OBSERVATIONS <br /> This was a surety release inspection conducted by Eric Scott of DRMS, accompanied by permittee <br /> representative Mike Volosin of Ames Construction. Because a 111 permit cannot be amended to add <br /> additional affected area, this 111 permit replaced the previous 111 Horton's Borrow permit (M2017-053) <br /> when expansion of the mined area was needed. The initial Horton's Borrow permit will be released so that <br /> the affected area is not covered by overlapping reclamation permits. <br /> Ames Construction requested release of the Front Range Feedlot Borrow 2 permit on August 24, 2018 and <br /> DRMS sent out release notification letters as required on August 28, 2018. To date no comments or <br /> objections have been received. The approved reclamation plan for the site is for an irrigation recharge pond <br /> (unlined but sloped excavation) surrounded by the approved reclamation vegetation consisting primarily of <br /> rangeland grasses. <br /> During the release inspection it was noted although the earthwork has been completed, no topsoil has been <br /> replaced surrounding the recharge pond, and no seeding has taken place (see photos 1-4). DRMS will deny <br /> the release request at this time because the approved reclamation has not been completed as approved. The <br /> area surrounding the recharge pond should be ripped, topsoil will need to be replaced, and seeding and <br /> mulching will need to be completed as described in the approved reclamation plan. <br /> Inspection Contact Address <br /> Mike Volosin <br /> Ames Construction, Inc. <br /> 18450 E.28th Ave <br /> Aurora,CO 80011 <br /> Enclosure: SLO1 Denial Letter <br /> Page 2 of 4 <br />