My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2018-06-28_INSPECTION - C1981019
DRMS
>
Day Forward
>
Inspection
>
Coal
>
C1981019
>
2018-06-28_INSPECTION - C1981019
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
7/2/2018 11:02:11 AM
Creation date
6/28/2018 10:36:55 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
C1981019
IBM Index Class Name
Inspection
Doc Date
6/28/2018
Doc Name
Inspection Report
From
DRMS
To
Colowyo Coal Company
Inspection Date
6/18/2018
Email Name
ZTT
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
12
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
June 18, 2018 C-1981-019/Colowyo Coal Mine ZTT <br /> <br /> <br />Number of Partial Inspection this Fiscal Year: 11 <br />Number of Complete Inspections this Fiscal Year: 4 <br /> <br /> Page 8 of 11 <br /> <br />Topsoil verification holes were dug throughout the East and West Pit areas being requested for Phase II bond <br />release found in SL-14 application. Colowyo is approved for variable topsoil depth placement and as per <br />Colowyo’s PAP, “After the final regrading is completed, the topsoil will be reapplied as shown on the disturbed <br />land areas shown on the Topsoil Handling Map (Map 28 and 28A). Future topsoil redistribution will be done at an <br />average depth of eight (8) inches based on the volumetric analysis of available materials and areas as presented in <br />Rule 2.05.” Due to the size of requested Phase II acreage (822 acres) the Division dug a total of 70 topsoil <br />verification holes, 36 in the East Pit and 34 in the West Pit. For each verification hole, a depth of at least 8 inches <br />was dug for each hole. Out of the 70 topsoil verification holes, a total of 5 were found to be between 4 - 8 inches. <br />The holes in which topsoil was found to be less than 8 inches in depth were all within the same region along upper <br />elevations of the reclamation areas. This remains consistent with Colowyo’s approved topsoil depth requirements <br />in the PAP. The remaining 65 topsoil verification holes were found to be greater than 8 inches in depth. For <br />location and information on the topsoil verif ication holes, please refer to the provided figure below. <br /> <br /> Topsoil verification holes. <br />
The URL can be used to link to this page
Your browser does not support the video tag.