Laserfiche WebLink
Permit Number C-1994-082 Page 17 of 17 <br />The original performance bond for the Yoast Mine including revisions was $5,095,689.00. For the <br />partial Phase I portion of this SL-6 bond release, Rule 3.03.1(2)(a) states that the Division can release up <br />to 60% of the entire amount. The 76.5 acres that are requested for Phase I bond release make up <br />approximately 8.99% of the 850.5 total disturbed acres. $3,057,413.40 constitutes 60% of the original <br />liability (60% of $5,095,689.00). Per Rule 3.03.1(2)(a), the Division can release up to $274,861.46 <br />(8.99% of $3,057,413.40) for this SL-6 partial Phase I bond release. <br /> <br />For the partial Phase III portion of this SL-6 bond release, Rule 3.03.1(2)(c) states that the Division can <br />release the remaining portion of the entire amount. The Phase III areas requested in the SL-6 Phase I <br />and II bond release have been approved, leaving 15% of the entire amount remaining. The 275.4 acres <br />that are requested for Phase III bond release make up approximately 32.39% of the 850.5 total disturbed <br />acres. $764,353.35 constitutes 15% of the original liability (15% of $5,095,689.00). Per Rule <br />3.03.1(2)(c), the Division can release up to $247,574.05 (32.39% of $764,353.35) for this SL-6 partial <br />Phase III bond release. <br /> <br />The most recent update of the reclamation liability for the Yoast Mine was completed on March 7, 2017 <br />during the Permit Renewal No. 4 (RN-4) review process. The Division determined that the estimate of <br />liability at the Yoast Mine was $1,902,423.58. The Division previously released $11,862.00 with SL-1, <br />$790,205.00 with SL-2, $1,693,918.00 with SL-3, $452,336.00 with SL-4, and $1,493.63 with SL-5. <br /> <br />The Division holds a performance bond of $2,221,677.26 for the Yoast Mine. The current liability for <br />the site is $1,902,423.58. The minimum amount that must be retained in accordance with Rule 3.03.1(3) <br />is $1,379,988.07 ($1,902,423.5 - $522,435.07 (SL-6 Phase I + Phase III)). The Division estimates its <br />cost to complete remaining reclamation work at the site to be $1,340,063.72. The Division proposes to <br />release $522,435.07 associated with the Phase I and Phase III portions of this SL-6 bond release. The <br />remaining $1,379,988.07 is sufficient to assure completion of the remaining reclamation work at the site <br />if the work had to be performed by the Division, including the cost of reestablishing vegetation on any <br />revegetated areas, should those areas fail. <br /> <br />Any person with a valid legal interest which might be adversely affected by this proposed decision may <br />request a formal public hearing before the Mined Land Reclamation Board in accordance with Rule <br />3.03.2(6). Public notice of this proposed decision will be published twice in the Steamboat Pilot as soon <br />as possible. Requests for public hearing must be submitted to the Division in writing within thirty days <br />of the first publication in the Steamboat Pilot. If no hearing is requested within those thirty days, the <br />Division's decision will become final. <br /> <br /> <br /> C-SL-10