Newmont Mining Corporation <br /> Cripple Creek&Victor Gold Mine <br /> HGM Platform Extension CQA <br /> NewFields Job No.475.0106.019 <br /> Wednesday,August 02,2017 <br /> FIELD DAILY PROGRESS REPORT <br /> PROJECT: HIGH GRADE MILL(HGM) PLATFORM EXTENSION <br /> SITE: CRIPPLE CREEK&VICTOR GOLD MINE(COLORADO) <br /> CONTRACTOR: SCHMUESER ASSOCIATES <br /> DATE: WEDNESDAY,AUGUST 02,2017 <br /> TEMPERATURE: LOW:44°F TO HIGH: 71°F <br /> WEATHER: MOSTLY CLEAR, AFTERNOON THUNDERSTORM WITH PRECIPITATION <br /> NEWFIELDS PERSONNEL ONSITE: ERIC NIEBLER, FIELD TECHNICIAN <br /> 1.0 EARTHWORKS <br /> 1.1 General <br /> Pot holing was performed by Schmueser Associates to locate utilities along the existing mill <br /> platform. Existing berms were moved back from the slope to perform work below the slope in <br /> the following days. <br /> 1.2 Subgrade <br /> No work performed during the shift. <br /> 1.3 Select Structural Fill(iSSF) <br /> No select structural fill was transported, placed, or compacted during the shift. <br /> 2.0 NEWFIELDS AND/OR CONTRACTOR FIELD/LABORATORY TESTING <br /> No sample collection or testing was performed during this shift. <br /> 3.0 MEETINGS AND COMMUNICATIONS <br /> NewFields personnel attended the Schmueser Associates Daily Safety Meeting. <br /> 4.0 ISSUES,CONCERNS, MISCELLANEOUS ACTIVITIES <br /> Surveyors from Foresight West staked the boundaries as well as additional locations within the <br /> limits of the platform extension. <br /> There was a discussion regarding the platform extension design drawings. Existing ground in <br /> the area of the platform extension did not match up with the design drawings making it <br /> Page 1 <br />