Laserfiche WebLink
To: Jared Ebert <br /> Date: January 2.2018 <br /> Page 28 <br /> Response to Comments 46 j <br /> Estimated Mobilization/Demobilization costs are included in the indirect costs shown in <br /> Attachment 6. <br /> Comment 47 <br /> If LRM, desires to bond the site in the phased manner as discussed above, please commit <br /> to not affecting land in a subsequent phase until the Division receives and approves of <br /> any financial warranty increase to cover the disturbance of the subsequent phase or the <br /> Division approves documentation that an increase in the financial warranty is not <br /> necessary. <br /> LRM will not affect land in a subsequent phase until the Division receives and approves <br /> of any financial warranty increase to cover the disturbance of the subsequent phase or <br /> the Division approves documentation that an increase in the financial warranty is not <br /> necessary. <br /> Response 47 <br /> LRM desires to bond the site in a phased approach and commits to not disturbing <br /> additional phases prior consulting with the Division to ensure adequate bond is in place. <br /> RULE 6.4.13 EXHIBIT M — OTHER PERMITS AND LICENSES <br /> Comment 48 <br /> Please see the enclosed correspondence from the Army Corps of Engineers regarding <br /> Section 404 of the Clean Water Act Initial Comments. Please respond as necessary. <br /> Response 48 <br /> LRM has reviewed the correspondence from the Army Corps of Engineers regarding <br /> Section 404 of the Clean Water Act and will take appropriate actions as warranted. No <br /> action is required at this time. <br /> Comment 49 <br /> Please see the enclosed correspondence from History Colorado. Please respond as <br /> necessary. <br /> Response 49 <br /> LRM has reviewed the correspondence from History Colorado and will take appropriate <br /> actions as warranted. No action is required at this time. <br /> Response to DBMS comments T E L E S T O <br />