Laserfiche WebLink
Newmont Mining Corporation <br /> Cripple Creek&Victor Gold Mine . <br /> Poverty Gulch QA <br /> NewFields Job No.475.0106.021 <br /> Monday October 16,2017 <br /> FIELD DAILY PROGRESS REPORT <br /> PROJECT: POVERTY GULCH DIVERSION CHANNEL <br /> SITE: CRIPPLE CREEK &VICTOR GOLD MINE (COLORADO) <br /> CONTRACTOR: CONLEY CONSTRUCTION <br /> DATE: MONDAY, OCTOBER 16, 2017 <br /> TEMPERATURE: LOW: 33°F TO HIGH: 62°F <br /> WEATHER: CLEAR SKIES, CLOUDS ROLLING IN FOR THE AFTERNOON <br /> NEWFIELDS PERSONNEL ONSITE: ROXANNE LI, FIELD TECHNICIAN <br /> 1.0 EARTHWORKS <br /> No earthworks were completed today. <br /> 2.0 GEOTEXTILE <br /> Geotextile was placed along the remainder of the channel with a minimum 6 foot overlap <br /> between panels. All geotextile has now been placed. <br /> 3.0 RIPRAP <br /> Riprap was placed from station 4+45 to station 5+20, to a depth of three feet in the bottom of <br /> the channel as indicated in the construction drawings. <br /> 4.0 CONCRETE AND GROUT <br /> No concrete or grout was poured today. <br /> 5.0 NEWFIELDS AND/OR CONTRACTOR FIELD/LABORATORY TESTING <br /> No testing was performed today. <br /> 6.0 MEETINGS AND COMMUNICATIONS <br /> No meetings were attended today. <br /> 7.0 ISSUES, CONCERNS, MISCELLANEOUS ACTIVITIES <br /> The exposed topsoil along the western side of the diversion channel was seeded. <br /> Page 1 <br />