Laserfiche WebLink
Exhibit E — Reclamation Plan <br /> structures, and for the use and development of on-site water resources. Since the <br /> area of surrounding lands is a mix of these uses, the site end use will retain these <br /> potentials. <br /> The rate of reclamation activity, including grading, soiling and revegetation will <br /> follow concurrently with extraction and the respective timetables identified for <br /> extraction under Exhibit D — Mining Plan. All timetables are contingent upon <br /> market conditions. With extraction activities anticipated to take up to 25-30 years <br /> to complete, reclamation will add an approximately five years to this estimate, <br /> bringing the anticipated life of the mine to 25-30± years, or the year 2045-50. The <br /> actual end point is five (5.0±) years subsequent to the completion of all recoverable <br /> materials and successful release of all reclamation required under the approved <br /> State of Colorado Division of Reclamation Mining and Safety (DRMS) permit. <br /> A Backfill Notice follows this page, as part of this Exhibit. The use of inert fill <br /> will facilitate the timely fill of selected portions of the project areas, and related <br /> reclamation of affected lands and use of related water resources (refer to Exhibit L <br /> — Reclamation Costs). <br /> Varra Companies, Inc. OMLR 112 Permit Application 4 <br /> Parcel 122—Resource Development Project 20 April 2017 <br />