March 28, 2017 <br />2.0 Critical Construction Periods <br />2.1 Removal of All Organic Material and Topsoil <br />Topsoil and organic material removal activities were not conducted during the quarter. <br />2.2 Placement of Underdrainage Systems <br />The underdrainage system was completed in the first quarter of 2010; additional work on this <br />system is not anticipated. During the time of the inspection, the water flow was approximately <br />0.25 gallons per minute (Photograph 4). <br />2.3 Installation of Surface Drainage Systems <br />Both the north and south surface drains were inspected (Photographs 5 and 6). At the time of <br />the inspection there was no water flow. There was stagnant water due to melting snow. <br />2.4 Placement and Compaction of Fill Materials <br />There was no placement of material or contour work done on the fill this quarter. All of the required <br />material for the fill has been placed and compacted. It's anticipated there will be no more <br />additional fill material placed on the fill. <br />Photograph 7 depicts the west facing slope of the fill in the area where the slope of the fill is at <br />3H: 1V. <br />Photograph 4: Water from the Underdrainage System (3/23/2017) <br />2 <br />