Albert Frei and Sons, Inc. Priola Pit <br /> Permit# M-2007-087 2017 Annual Report <br /> Notes: <br /> 3. We estimate we have 3 to 6 months of work left to complete reclamation once <br /> the landowner resolves his problems. The level parts of the mine does not have to <br /> be resoiled since that area is designated as development area. A Technical <br /> Revision was approved on 3/22/16 to extend the reclamation completion for 3 <br /> years as litigation was taking place time. See 19. <br /> 9. This area is filled and is waiting final grading to reach the final elevations. See <br /> 19. <br /> 12. Once final side slopes are done they will be seeded. We seeded 0.88 in the <br /> spring of 2010 and the grass is growing. See 19. <br /> 13. Status of weed control is unknown, see 19. <br /> 16. There is no water exposed on the mine area. <br /> 19. We still have an active contract, but landowners are denying access to the <br /> mine at this time so everything is on hold. <br />