Pond NHN-002 & NHN-002 Ditch Designs <br />Introduction <br />Pond NHN-002 at the New Horizon North Mine is designed to capture and contain the runoff <br />from the 10 -YR, 24 -HR storm event as part of sediment control at the mine. This appendix <br />contains design specifications for Pond NHN-002 and its feeding ditches, NHN-002 North and <br />NHN-002 South. Included in these designs are the stormwater runoff values for the 10 -YR, 24 - <br />HR event that the ditches and pond must contain and control and the 25 -YR, 24 -HR event that <br />the pond must pass safely through its emergency spillway. <br />Stormwater Data <br />Pond NHN-002 is the sediment pond for the stormwater drainage watershed SW2 shown on Map <br />2.05.3(4)-1. Runoff from this area flows entirely to the ditches that feed Pond NHN-002 or the <br />pond itself. Map 2.05.3(4)-9 shows the breakdown of SW2 into sub -watersheds that each feed a <br />separate part of the Pond NHN-002 stormwater control system. SW2-A feeds NHN-002 South, <br />SW2-13 feeds the pond directly, and SW2-C feeds NHN-002 North. Table 2.05.3(4)-8-1 shows a <br />summary of the runoff values for each sub -watershed. This data can also be seen in SEDCAD <br />models located in this Appendix. In addition to the sub -watersheds, Pond NHN-002 also will <br />handle pit pumping, which can be seen in the Table 2.05.3(4)-8-1. The10-YR runoff and peak <br />flows are from SEDCAD Model 1 (As shown later in this Appendix); the 25 -YR peak flow is <br />from SEDCAD Model 2 (As shown later in this Appendix). <br />Table 2.05.3(4)-8-1 Summary of Sub -watershed Runoff Values <br />Sub -watershed <br />Area <br />10 -YR, 24 -HR <br />25 -YR, 24 -HR <br />Acreage <br />Peak <br />Discharge <br />(cfs) <br />Runoff <br />Volume <br />(ac -ft) <br />Peak <br />Discharge <br />(cfs) <br />Runoff <br />Volume <br />(ac -ft) <br />SWS2-A <br />15.20 <br />14.73 <br />1.41 <br />SWS2-B <br />44.10 <br />39.58 <br />4.05 <br />SWS2-C <br />26.60 <br />26.89 <br />2.50 <br />Pit Pumping* <br />N/A <br />2.00 <br />0.16 <br />SWS2 Total <br />85.90 <br />83.20 <br />8.12 <br />1 113.40 <br />11.23 <br />*Pit pumping is the same regardless of storm size <br />Sediment Pond Design <br />Pond NHN-002 can be seen on Map 2.05.3(4)-9, along with its associated ditches. Map <br />2.05.3(4)-9 also shows cross sections of the pond design along with design information for the <br />ditches. Pond NHN-002 will be fed by both direct drainage and its two ditches. Discharge from <br />Pond NHN-002 will be controlled via a gated pipe system that has been used with great success <br />at other similar sediment ponds. An 18 -inch diameter pipe with a pair of valved 6 -inch diameter <br />Appendix 2.05.3(4)-8 Page 1 April 2016 (PR -01) <br />