• Remediation efforts began at the uppermost and lowermost affected lifts <br />simultaneously. Primary focus centered on reestablishing safe egress routes along <br />affected benches and securing overall stability. Cosmetic work is ongoing. <br />• All released solution remained on liner and would have reported to operational <br />recovery systems. Due to sub -freezing temperatures occurring at the time of the <br />event a small amount of solution on the 9800 level did become frozen. Any frozen <br />solution will slowly thaw as temperatures increase, draining down to the liner and <br />captured by existing solution recovery systems. <br />b. Any known or adverse impacts to human health, property or the environment <br />As all solution and washed out material remained on liner and the immediate response <br />short time frame between the event and the remediation process, no known impacts to <br />human health or the environment have been observed or are expected. to occur. <br />c. CC&V Contact <br />For any further information regarding this event please contact; <br />Meg Burt <br />Senior Environmental Manager <br />PO Box 191, <br />100 N ars St, <br />Victor, Colorado, 80860 <br />Work: 719-689-4055 <br />Cell: 775-397-3571 <br />Fax: 719-689-3254 <br />d. Monitoring and analyses that are necessary to evaluate the situation and <br />corrective actions <br />As the failure occurred on a lined facility there are no impacts expected to human health <br />or the environment that require monitoring or analysis. <br />Daily inspection of the remediation effort will be conducted by operational personnel. If <br />any changes are observed within the facility the Geotechnical department will be <br />immediately notified. <br />The Site Geotechnical Department initially inspected the location on the morning of <br />January 4th, 2017 and it was determined that the washout did not pose stability issues to <br />the heap leach facility. The washout only affected in the vicinity of the crevice itself and <br />there were no additional visual indications for this area to become larger. There were no <br />cracks around the crevice. <br />A follow up inspection was completed on January 11th to evaluate the progress of <br />remediation works which verified no visual indications of any stability issue for the heap <br />(Figure 3). <br />