Cripple Creek & Victor Gold Mining CompanySquaw Gulch Valley Leach Facility Phase 1 CompletionGeomembrane Panel Deployment SummaryLength (ft)Width (ft) Area (ft²) Area (ft²) Cumulative Area (ft²)Deployment DatePanel NumberRoll NumberAmbient Temp.(°F)Average Thickness (mm)RemarksQA MonitorApproximate QuantitiesSurveyed Quantities7/13/2016P‐20003550746280DW11922.52,6782,3016,123,8207/13/2016P‐20013550746580DW24822.55,5804,8946,128,7147/13/2016P‐20023540496580DW24922.55,6034,9506,133,6647/13/2016P‐20033540496780DW12522.52,8132,4596,136,1237/13/2016P‐20043540506780DW124121,4881,2036,137,3267/13/2016P‐20053540506780DW12322.52,7681,2016,138,5277/13/2016P‐20063540506780DW24822.55,5804,8896,143,4167/13/2016P‐20073550676280DW24822.55,5804,9286,148,3447/13/2016P‐20083550676780DW12522.52,8132,4066,150,7507/13/2016P‐20093540526880DW12522.52,8132,4726,153,2227/13/2016P‐20103540526980DW24522.55,5134,7996,158,0217/13/2016P‐20113570997980DW622.51351036,158,1247/14/2016P‐20123550756080DW25122.55,6484,8846,163,0087/14/2016P‐20133550756380DW12222.52,7452,3576,165,3657/14/2016P‐20143550716380DW13022.52,9252,5336,167,8987/14/2016P‐20153550716580DW23922.55,3784,7456,172,6437/14/2016P‐20163550696580DW1122.52482176,172,8607/14/2016P‐20173550696580DW24422.55,4904,8896,177,7497/14/2016P‐20183550697780DW10122.52,2732,1496,179,8987/14/2016P‐20193560777780DW13722.53,0832,7116,182,6097/14/2016P‐20203560777780DW23722.55,3334,6596,187,2687/14/2016P‐20213570997780DW1222.52702316,187,4997/14/2016P‐20223560766580DW24222.55,4454,9066,192,4057/14/2016P‐20233560766780DW12822.52,8802,4686,194,8737/14/2016P‐20243550686780DW12022.52,7002,3476,197,2207/14/2016P‐20253550686780DW24922.55,6034,7296,201,9497/15/2016P‐20263560786580DW24822.55,5804,9526,206,9017/15/2016P‐20273570997680DW11252752076,207,1087/15/2016P‐20283570997680DW24184323706,207,478Gray text reflects panels deployed outside of thePhase 1 Completion certification boundary.Page 70 of 87
|