Newmont‐Cripple Creek & Victor Gold Mine  <br />Technical Specification No. 02200.DOCX  <br />Squaw Gulch VLF  <br />Project No.475.0106.006  <br />June 15, 2016  <br />  <br />  <br />  <br />Page 7  <br />D. CONTRACTOR shall  grade  topsoil  stockpiles  to  prevent  erosion  and  ponding  of  <br />precipitation  in  the  stockpile  areas.  The  maximum  topsoil  stockpile  height  will  be  <br />approved  by MANAGER.  The CONTRACTOR shall  protect  stockpiled  topsoil  by  an  <br />effective cover of non‐noxious, quick‐ growing, annual, and perennial plants, approved  <br />by MANAGER, which shall be seeded or planted during the first appropriate growing  <br />season after removal.  <br />3.3. Waste Removal  <br />Waste  material  is  defined  as  material  too  wet,  too  dry,  frozen or  containing  ice  or  snow,  <br />containing  organic  or  other  deleterious  matter,  having  poor  characteristics  of  grading  or  <br />compaction, having other characteristics that may result in undesirable settlement or other  <br />movement of the fill, or within the fill, or otherwise not meeting the requirements of the  <br />SPECIFICATIONS, provided that this definition permits drying, water, and any other processing  <br />or reprocessing to make the material stable and suitable prior to incorporating it into the fill as  <br />permitted in the SPECIFICATIONS or by the MANAGER and CERTIFYING ENGINEER.  <br />A. CONTRACTOR shall  excavate  and  remove  waste  in  a  manner  that  will  minimize  <br />contamination with other soil horizons.  <br />B. CONTRACTOR shall stockpile removed waste at locations designated by MANAGER  <br />3.4. Excavation  <br />A. CONTRACTOR shall  perform  excavation  to  the  lines  and  grades  shown  on  the  <br />DRAWINGS or as directed by MANAGER.  No  excavation  shall  begin  until  the  <br />CONTRACTOR has provided construction staking for the proposed work.  <br />B. CONTRACTOR shall prevent the disturbance of surrounding areas during excavation.  <br />Where selective excavations are required to obtain materials for Structural Fill and  <br />Select Structural Fill, the material removed from the excavations shall be taken directly  <br />to the fill areas or, if required, stockpiled by material types. The stockpiles shall be  <br />approved by MANAGER.  <br />C. CONTRACTOR shall grade all excavations to ensure grades are maintained to provide  <br />adequate drainage at all times. Work shall be suspended by CONTRACTOR when, in the  <br />opinion of MANAGER and CERTIFYING ENGINEER, the site is overly wet, muddy, or  <br />otherwise unsuitable for proper maintenance, until directed otherwise by MANAGER,  <br />at no cost to CC&V.  <br />D. In excavations where Structural Fill or Select Structural Fill is to be placed on slopes  <br />steeper than 3H:1V, horizontal benches shall be excavated into the slope to allow fill to  <br />be  placed  in  horizontal  lifts.  The CONTRACTOR shall  continuously  bench  and  key  <br />embankment material into the existing material a minimum of 2 feet.