Laserfiche WebLink
<br />Proposed Decision and Findings of Compliance September 2016 <br />Partial Phase I Bond Release SL-09 Page 9 <br />Table 3. Summary of Applicable SL-09 Bond Release Amounts <br /> <br />Task Cost <br />Doze Remaining West Pit Highwall $ 242,194.00 <br />Doze Remaining West Pit Highwall $ 3,660,532.00 <br />Load and Haul Spoil to West Pit $ 485,491.00 <br />Rip Remaining West Pit Highwall $ 122,204.00 <br />Finish Grade West Pit $ 148,086.00 <br />Excavate Regraded Areas for Post-mining Drainage Channels $ 45,578.00 <br />“Mine” Riprap from South Taylor Pit Stockpiles $ 174,397.00 <br />Regrade East Taylor Pond $ 5,171.00 <br />Regrade West Pit Pond $ 14,417.00 <br />Remove and Regrade East Taylor Pond Ditch $ 1,667.00 <br />Remove and Regrade West Pit Coal Road Ditch $ 2,188.00 <br />Haul Topsoil from Pile 4A to West Pit $ 127,369.00 <br />Haul Topsoil from Pile 15B to West Pit $ 409,026.00 <br />Haul Topsoil from Pile 15K to West Pit $ 75,996.00 <br />Haul Topsoil from Pile 16A to West Pit $ 96,167.00 <br />Haul Topsoil from Pile 16E to West Pit $ 34,314.00 <br />Haul Topsoil from Windrow 5 to West Pit $ 33,387.00 <br />Replace Topsoil from Stockpile to East Taylor Pond $ 1,614.00 <br />Replace Topsoil from Stockpile to West Pit Taylor Pond $ 2,943.00 <br />Reseed West Pit with Grazing Land Seed Mix $ 622,391.00 <br />Reseed West Pit with Sagebrush Steppe Seed Mix $ 161,388.00 <br />Reseed East Taylor Pond with Grazing Land Seed Mix $ 937.00 <br />Reseed West Pit Pond with Grazing Land Seed Mix $ 1,709.00 <br />Mobilize/Demobilize Equipment $ 236,792.00 <br />Site Maintenance During Ten Year Liability Period $ 76,039.00 <br />Subtotal of direct costs (rounded to nearest dollar) $ 6,781,997.00 <br />Indirect Costs (rounded to nearest dollar) $ 1,129,442.00 <br />Total Amount $ 7,911,439.00 <br />Applicable Amount (~7%) $ 579,166.00 <br />Total Bond Release Amount (60% of Applicable Amount) $ 347,500.00 <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br />