33 Mobe&Demob (19)
<br /> TAB 33(Section 19.0) Amendment No.11-MOBILIZATION AND DEMOBILIZATION
<br /> CALCULATED AT 2%OF THE THE EQUIPMENT COSTS+LABOR COSTS FOR EARTHMOVING PROJECTS
<br /> Section Management Unit Equipment Cost Labor Cost Total Eqpt and Labor
<br /> 4.0.1 ECWH $ 3,010,617 $ 365,874 $ 3,376,491
<br /> 4.0.2 WHEX $ 2,238,789 $ 329,941 $ 2,568,730
<br /> 4.0.3 North Cresson $ 2,098,768 $ 341,882 $ 2,440,650
<br /> 4.0.4 Main Cresson $ 1,286,661 $ 222,798 $ 1,509,459
<br /> 4.1.1 Chicago Tunnel $ 17,523 $ 5,007 $ 22,530
<br /> 7.1 AGVLF $ 54,818,653 $ 5,318,940 $ 60,137,593
<br /> 7.2 SGVLF $ 34,559,020 $ 3,068,749 $ 37,627,770
<br /> 7.3 Mill Platform $ 155,178 $ 53,236 $ 208,414
<br /> 7.4 AJAX Pads3&4 $ 53,556 $ 11,528 $ 65,085
<br /> 8.1 ECOSA $ 2,612,590 $ 366,816 $ 2,979,406
<br /> 8.2 SGOSA $ 1,233,646 $ 223,315 $ 1,456,961
<br /> 8.3 Ironclad Corridor $ 119,272 $ 27,367 $ 146,638
<br /> 8.4 GM Piles $ 19,807 $ 19,842 $ 39,649
<br /> Total $ 102,224,080 $ 10,355,295
<br /> Mobilization $ 1,022,240.80 $ 103,552.95 $ 1125794
<br /> SAlnc Revision 8-10-16 -Removed Providence Mine from Table
<br /> 8/10/2016