Laserfiche WebLink
Albert Frei and Sons, Inc. Priola Pit <br /> Permit# M-2007-087 2016 Annual Report <br /> Notes: <br /> 3. We estimate we have 3 to 6 months of work left to complete reclamation once <br /> the landowner resolves his problems. The level parts of the mine does not have to <br /> be resoiled since that area is designated as development area. Reclamation <br /> activities are ongoing when material needed for backfilling is available. A <br /> Technical Revision was approved on 3/22/16 to extend the reclamation completion <br /> for 3 years as litigation is taking place at this time. <br /> 9. This area is partially filled and is waiting final grading to reach the final <br /> elevations. <br /> 12. Once final side slopes are done they will be seeded. We seeded 0.88 in the <br /> spring of 2010 and the grass is growing. <br /> 16. There is no water exposed on the mine area. <br />