Wildcat Mining Corporation <br />July 18, 2016 <br />Page 2 <br /> <br />Page 2 of 2 <br />shall revegetate the entire slope in accordance with the revegetation plan approved through <br />TR-5 within 30 days. <br />Additionally, the TR-7 request provides details regarding the field modifications implemented <br />during construction of the Chief Portal slope. The details, however, are not adequate to provide the <br />Division with confidence in the long term stability of the slope. In accordance with Rule 6.5, WMC <br />shall provide to the Division an engineering stability analysis of the slope within 30 days. <br />If you require additional information, or have questions or concerns, please contact me at the <br />Division’s Grand Junction Field Office. <br /> <br />Sincerely, <br /> Dustin Czapla <br />Environmental Protection Specialist <br />Department of Natural Resources <br />Division of Reclamation, Mining and Safety <br />101 South 3rd, Suite 301 <br />Grand Junction, CO 81501 <br />Phone: (970) 243-6299 <br />Fax: (970) 241-1516 <br /> <br /> <br />Cc: Russ Means, DRMS GJFO <br /> Lucas West, DRMS GJFO <br /> Tony Waldron, DRMS Denver <br /> Jeff Fugate, DRMS AGO <br /> <br />Attachment: June 30, 2016 Inspection Report, LJW <br /> <br /> <br /> <br /> <br /> <br />