IV. PROPOSED DECISION <br />Based upon the above observations, the Colorado Division of Reclamation, Mining and Safety <br />proposes to partially approve Seneca Coal Company's (SCC) request for a Partial Phase I Bond <br />Release, SL-O1, for the Yoast Mine. The proposed decision will release the applicant from the <br />liability for backfilling, grading and drainage reestablishment, as discussed in this document. SCC <br />requested a Partial Phase I Bond Release for 188.1 acres. The Division is excluding 15.08 acres from <br />the Partial Phase I Bond Release allowing 173.02 acres proposed for release. The Division is <br />excluding the following areas (as shown on the Figure "Yoast Phase I Bond Release SL-Ol Map - <br />Zoom Area"): the remaining light-use road that runs along the northern portion of the proposed bond <br />release azea (4.90 acres), an area of gullies on the south and west edge of the proposed bond release <br />area (6.25 acres), a highwall crack on the north and east edge of the proposed bond release area (0.81 <br />acres), the entire length ofpost-mining drainage channel 10 (YPM-10, 1.37 acres), the entire length of <br />post-mining drainage channel 13 (YPM-13, 1.31 acres) and the gully area above (southwest of) YPM- <br />13 (0.44 acres). Although Pond O11 A (0.85 acres) is within the North Pit bond release area, the pond <br />itself is not being released with this Phase I bond release. <br />PHASEIBOND RELEASE <br />The Division currently holds a corporate surety in the amount of $5,200,000.00 from the Seaboard <br />Surety Company (CS329873) for the Yoast Mine. The required surety for the Yoast Mine, prior to <br />the Partial Phase I Bond Release, is $5,046,639.00. SCC requested a release of $611,023.00 in the <br />Phase I bond release application. The Division is proposing to release $11,862.00. Pursuant to Rule <br />3.03.1(2) (a), "Up to sixty percent of the applicable bond shall be released when the permittee <br />successfully completes backfilling, regrading and drainage control in accordance with the approved <br />reclamation plan." The required bond liability for the Yoast Mine will be $5,034,777.00. The <br />Division finds that this amount is sufficient to complete the approved reclamation plan at the Yoast <br />Mine if the work had to be performed by the Division. <br />The reason there is such a large difference in the amount SCC has requested for release and the <br />amount the Division is proposing for release is detailed below. <br />The Division uses a floating bond concept for backfilling and grading to calculate the reclamation <br />cost estimate and, consequently, the required bond amount. During the initial five-year permit term <br />of a surface mine the Division determines aworst-case disturbance for the mine and sets a liability <br />amount for the mine's reclamation. This worst-case disturbance is based on a single year during the <br />five-year permit term in which the greatest disturbance will occur. As the operator continues to mine <br />during that permit term, the dollazs associated with the backfilling and regrading of a specific pit are <br />"floated" to the next pit in the sequence. During successive five-yeaz permit terms, the Division <br />performs aworst-case disturbance analysis for that permit term. If the worst-case disturbance is <br />greater than it was in previous permit terms, the amount of bond required for backfilling and <br />regrading is increased. If the worst-case disturbance is less than it was in the previous permit terms, <br />the amount of bond required for backfilling and regrading remains constant (it is only adjusted for <br />changes in equipment costs). In this way the monetary liability is "floated" from one pit to the next <br />so that the only pit that has actual dollazs associated with it is the pit that is currently open (or the <br />12 <br />