June 27, 2016 <br />2.0 Critical Construction Periods <br />2.1 Removal of All Organic Material and Topsoil <br />Topsoil and organic material removal activities were not conducted during the quarter. <br />2.2 Placement of Underdrainage Systems <br />The underdrainage system was completed in the first quarter of 2010; additional work on this <br />system is not anticipated. During the time of the inspection, there was approximately one gallon <br />per minute of water flow. <br />2.3 Installation of Surface Drainage Systems <br />Both the north and south surface drains were inspected (Photographs 4 and 5). At the time of <br />the inspection there was no water flow in either drainage. The upper drain was inspected and <br />was in excellent condition. <br />Photograph 4: North Surface Drain Looking Northeast (6/24/2016) <br />