facilities will involve the following sequential activities, as briefly described in the following sections and shown <br />on the design drawings provided in Exhibit 49R: <br />• Completion of environmental and engineering investigations <br />• Placement of disturbed area markers <br />• Temporary drainage and sediment control measures <br />• Recovery and stockpiling of available soil materials <br />• Installation of drainage and sediment control structures (includes two -cell sedimentation pond) <br />• Construction of a light -use road and site preparation for shaft pad <br />• Construction of the shaft pad and lined cuttings pit <br />• Drilling and casing of an exploration borehole to verify geologic and groundwater conditions <br />• Substation construction and installation of electrical distribution line and equipment <br />• Grouting operations (as necessary) and drilling of shaft pilot holes <br />• Excavation and construction of shaft collar structures <br />• Blind -drilling and casing of two shafts <br />• Installation of mine ventilation fan, fan shroud, silencer, equipment building, and associated equipment and <br />controls on ventilation exhaust shaft <br />• Installation of shaft heater and associated ancillary equipment on ventilation intake shaft <br />• Erection of escape hoist building and installation of equipment and controls on ventilation intake shaft <br />• Construction of security fence around shafts <br />• Extension of entries from the 18 -Left longwall panel to connect to the shaft bottom <br />• Conversion of the exploration borehole to a Mine Atmosphere Control borehole, and installation of <br />modular methane drainage and/or nitrogen injection systems <br />• Boring and casing of a mine dewatering borehole and installation of a pumping system and controls <br />• Boring and casing of utility borehole and installation of rock -dust drop pipe, rock -dust tank and controls, <br />and compressed -air pipe <br />• Installation of compressor building, compressors, and associated control equipment <br />• Installation of a mine water transfer pipeline, associated valving, and access manholes <br />• Final clean-up and dressing of roads and site pad <br />Site-specific investigations required for design and permitting of the new ventilation shaft and pipeline will, or have <br />included a cultural resource survey of potential disturbance areas, soil and foundation characterization as the basis <br />for shaft pad and access road design, vegetation community mapping, and verification of TES compliance. The <br />cultural resource survey was conducted by Metcalf Archaeological Consultants, the engineering soils <br />characterization by Northwest Colorado Consultants, and the soils/vegetation investigations by Habitat <br />Management. The perimeter of all areas affected by surface facilities construction will be clearly marked before <br />the beginning of surface disturbances. The proposed shaft pad and cuttings pit will have maximum dimensions of <br />approximately 425 x 500 feet (4.5 acres) with cut and fill slopes, and the substation area will be approximately 80 x <br />125 feet. The substation and powerline disturbance, light -use road, and soil stockpile area will add approximately <br />1.1 acres of disturbance, for a total disturbed area of approximately 5.6 acres. The light -use road disturbance <br />corridor will be approximately 420 feet long and 40 feet wide (0.3 acres of disturbance). Actual constructed road <br />width (finished top width) is expected to be approximately 24 feet. Refer to Exhibit 25Y, 18LT Ventilation Shaft <br />Installation — Foundation and Road Investigations, Map 24 (Sheet 4 of 4), and Exhibit 49R, 18LT Ventilation Shaft <br />Installation — Design Drawings, for details on the road, and the road profile and cross-section. The proposed light - <br />use road crosses upland areas where road construction will involve removal of any large vegetation and stripping <br />and stockpiling of other vegetation, soil, and organic materials. <br />In order to reestablish effective vegetative cover, TCC will recover and stockpile a maximum of 18 inches of soil <br />material from shaft disturbance areas. With a total road disturbance area of approximately 0.3 acres, approximately <br />750 CY of soil material will be salvaged from the road corridor, and approximately 12,800 CY from the 5.3 acre <br />shaft pad and associated disturbance areas. Prior to initiation of soil salvage operations, temporary sediment <br />control measures (silt fence, wattles, and/or other, as appropriate) will be installed. Soil salvage volumes are <br />indicated on Table 49A. Soil material from the road corridor and other disturbance areas will be stockpiled in a <br />central soil stockpile areas as shown on the design drawings in Exhibit 49R. Natural vegetative materials (mulch) <br />MRI 1-259 2.05-45.16 11/28/11 <br />