Laserfiche WebLink
Newmont Mining Corporation ■ <br /> Cripple Creek&Victor Gold Mine ■ <br /> Squaw Gulch VLF CQA <br /> NewFields Job No.475.0106.006 <br /> Week Ending Saturday,April 2,2016 <br /> 1.5 Soil Liner Fill (SLF) <br /> SLF processing continued throughout the week at Dump 1. CAT 777 haul trucks were utilized to <br /> haul SLF material from the south east side of Dump 1 to the Dump 1 Processing area. <br /> Approximately 96,209 dry tons of material has been processed as of Saturday, April 2, 2016. <br /> 2.0 GEOSYNTHETICS <br /> 2.1 Geogrid <br /> No activities performed during this reporting period. <br /> 3.0 STORM WATER MANAGEMENT <br /> Best Management Practices continued to be performed. <br /> 4.0 NEWFIELDS LABORATORY ACTIVITIES <br /> NewFields personnel performed sieve analysis, atterberg limits, and compaction testing. <br /> Two samples of Soil Liner Fill (NF-SLF-8-C and NF-SLF-9-C) were collected from the processing <br /> plant. <br /> 5.0 MEETINGS AND COMMUNICATIONS <br /> NewFields personnel attended the weekly Contractor Planning Meeting (March 29, 2016), <br /> Ames daily safety meetings, weekly Contractor Safety Meeting (March 31, 2016) and NewFields <br /> daily safety meetings. <br /> 6.0 MISCELLANEOUS, ISSUES AND CONCERNS <br /> On March 31, 2016, snow began at approximately 13:00; however, Structural fill placement <br /> continued through the remainder of the shift. NewFields personnel ensured that Ames was <br /> clearing all snow in the Structural Fill placement area prior to placement. <br /> Page 3 <br />