Laserfiche WebLink
The water pumped from the Area 1 Pit can go in one of four directions, or a combination of them: 1) Pit to <br />Washplant I; 2) Pit to Washplant II; 3) Pit to mine water recycling line; and/or 4) Discharge to Foidel Creek. The <br />water pumped from the pit is piped to a de -sander, located at an old well site. From this point it is piped to one or <br />both of the washplants or piped over and tied into the existing mine water line. A line has been installed from the <br />de -sander back to the pit so that the back-flush water can be returned to the pit. The location of the lines is shown <br />on Map 24. The trenches were dug with a backhoe or trackhoe. During the excavation process suitable plant <br />growth media was removed and windrowed adjacent to the trench and then replaced on top of the sub -soils returned <br />to the trench. <br />PRI 5-1 1 2.05-97.8 02/01/16 <br />