Table 2.05.3-3 Approximate Timing of Operations <br />ITEM <br />DESCRIPTION <br />DATE <br />1 <br />Relocate 2 nd Park Lateral to pipeline <br />Fall 2011 <br />2 <br />Construct Surface Facilities; Extend or Relocate Utilities <br />Fall 2012 — Spring 2013 <br />3 <br />Complete mining at NH2; Move Equipment to NHN <br />Mid -2013 <br />4 <br />Mine NHN Area <br />Mid -2013 — Mid -2020 <br />5 <br />Relocate 2nd Park Pipeline to Original Ditch Location <br />2017 <br />6 <br />Re -topsoil and re -vegetate final cut area <br />2021 <br />7 <br />Continue to irrigate & monitor reclaimed areas until final <br />bond release <br />2031 <br />Section 2.05.3 Page 6 February 2016 (MR -16) <br />