CRIPPLE CREEK &VICTOR GOLD MINE <br /> NEWMONT MINING CO. amec <br /> SQUAW GULCH VLF WEEKLY REPORT foster <br /> wheeler <br /> Underground Workings: <br /> Blasting: <br /> None. <br /> Confirmatory Drilling: <br /> UG #6477: Sandvik 700—8.0 hours, 1000LF. Further remediation required. <br /> Remediation: <br /> UG#6679: A John Deere excavator removed shot rock in preparation for geogrid <br /> subgrade. Further remediation required. <br /> UG #6455 & UG #6456: A Cat excavator and Cat dozers removed shot rock in <br /> preparation for geogrid subgrade. Further remediation required. <br /> Underdrain System: <br /> Primary Underdrain: Complete. <br /> Secondary Underdrain: None. <br /> Tertiary Underdrain: None. <br /> Leak Detection: <br /> None. <br /> Geomembrane: <br /> None. <br /> Miscellaneous: <br /> None, <br /> II) Storm Water Management <br /> Best Management Practices (BMPs) continued to be performed. <br />