Applegate <br /> Group, inc. <br /> Water Resource Advisors for the West <br /> DAILY CONSTRUCTION REPORT <br /> Date: 12/7/2015 Job Name: Brannan Pit 29—TR 2.2 Report No. 1 <br /> AG Project#: 10-116 1 Client: Brannan Sand and Gravel <br /> Daily Overview: Drain line installation Time on Site: 11:30 am <br /> Weather: 56'F, mostly cloudy, no precipitation <br /> Principals on Site: Tom—Brannan; Tom and Carrie—Applegate <br /> Equipment Data: front end loader <br /> 2 excavators 2-well point piston pumps <br /> Work Performed Today: <br /> Contractor is installing ADS N-12 slotted pipe along southern boundary of property. <br /> Excavator trenching and placing granular material, laborers placing pipe, excavator placing <br /> additional material, laborers placing geofabric wrap around filter material, additional granular fi I I <br /> placed on top of granular fill, backfill with native soils over the granular material. 1/3 to 1/2 of <br /> the pipe has been placed along south boundary. <br /> Manholes and solid wall pipes are onsite and stockpiled. Solid wall pipe has been installed for <br /> about 1/4 of the western boundary along with one manhole base. <br /> Contractor has installed a wellpoint piston pump system to control groundwater during <br /> construction. The pump manifold extends along the entire southern boundary of the drain limits. <br /> The contractor indicated that the well points are approximately 17-ft below grade to control <br /> groundwater during drain line installation. The pumps discharge into the dewatering ditch for the <br /> gravel pit. The standing water in the adjoining parcel has been significantly drawn down by the <br /> dewatering system. <br /> 1490 West 121'Avenue,Suite 100 (303)452-6611 •Fax:(303)452-2759 <br /> Denver,Colorado 80234 www.applegategroup.com <br /> 1 <br />