Laserfiche WebLink
Objection to DRMS' Surety Increase Request <br />January 14, 2016 <br />Page 3 of 5 <br />Which brings us to the TR -3 application of October 13, 2009, which addressed solely the <br />proposed reclamation of the bench on which Ca1X proposed to erect a rockdust mill <br />Pertinent portions of the TR -3, approved by DRMS on January 27, 2010, read as follows: <br />"Reclamation of the pad area [hereinafter, the "mill bench"] will be completed using the <br />current reclamation plan for the site." <br />"Flat areas will be topsoiled with stockpiled material and seeded." <br />"The disturbed 1H:1V slope [that is, the slope that existed, before construction of the <br />rockdust mill, on the bench where such mill was to be erected] will be backfilled to a <br />2H:1 V slope." [Much of this backfilling has already been accomplished.] <br />In a table that was incorporated into the TR -3 application, Ca1X noted that, at the time of <br />such application, it was aware of some 1,600 cubic yards of stored topsoil. <br />Errors in the November 2, 2011 Surety Increase Demand ("the Czapla Demand"): <br />In light of all of the foregoing, it is now apparent that the Surety Increase Demand of <br />November 2, 2011 (which took Ca1X Minerals' Surety amount from $41,400 to the <br />current $122,793, an increase of $81,653, or some 198% of the then -existing Surety) was <br />erroneous with respect to each of the following claimed "tasks", with consequent `over- <br />charging' of Ca1X — in 2011 — of some $64,000, as detailed below: <br />a. Task Ola, for which DRMS then demanded $40,164.93 in additional surety, to <br />assure "Demolition and/or removal of onsite facilities and structures", allowed no salvage <br />value for the rockdust mill and building, and various other improvements within such <br />building, all of which were achieved by Ca1X only after investing $2.5 million. <br />b. Tasks 03a, 03b, 03c and 03d, for which DRMS demanded a total of $23,795.06 in <br />additional surety, purported to accomplish the movement of some 23,148 cubic yards of <br />backfill material to the "process bench" [that is, the bench immediately above the mill <br />bench] and also to accomplish the transport to, and spreading upon, such bench of some <br />1,936 CY of topsoil. <br />There are two significant problems, here: first, the purportedly -required "backfilling and <br />dozing" is happening on a continuous basis, in order to assure that Ca1X can remain in <br />operation; and second, Mr. Czapla asserted, by this November 2, 2011 demand for <br />increased Surety, that Ca1X Minerals was obliged to distribute on the "process bench" <br />topsoil that had never been removed from such bench, and was, moreover, obliged to <br />distribute on such bench more topsoil than was actually available to CaJX. <br />c. Under Tasks 04a and 04b — which relate to the reclamation of the mill bench — it <br />was asserted by Mr. Czapla that $4,078.26 would be required to move, doze and/or apply <br />