<br /> <br />Section 01400.1 Page 8 of 10 January 14, 2011 <br />Earthworks CQA Plan Revision 0 <br /> <br />S:\Projects\1125G Squaw Gulch Valley Leach Facililty Design\I - Tech Specs\01400.1.r0.doc <br /> <br />7.06 CONSTRUCTION CERTIFICATION REPORT: <br /> At the completion of the project, the CQA Monitor shall submit to MANAGER a Construction Certification <br />Report. This report shall certify that the work has been performed in compliance with the DRAWINGS and <br />SPECIFICATIONS and will contain the following information: <br /> summary of all construction activities; <br /> photographic documentation; <br /> test data sheets; <br /> copies of weekly reports; <br /> CQA test results, including date, test locations and resolutions of deficient test results; <br /> copies of surveyors certificate; <br /> fill temperature monitoring results; <br /> staff schedule summary; <br /> a description of significant construction problems and the resolution of these problems; <br /> changes to the DRAWINGS or SPECIFICATIONS and the justification for these changes; <br /> record drawings, and <br /> a statement certifying that construction was completed in compliance with the DRAWINGS <br />and SPECIFICATIONS, signed, and sealed by the CERTIFYING ENGINEER registered in <br />the State of Colorado.