Table 2.05.3(3)-3 <br />Timing of Road, Ditch, and Utility Detours and Restorations <br />Item <br />Description <br />Date <br />1 <br />Construct BB Road Detour <br />2000 <br />2 <br />Installed 26" & 12" pipeline to divert West Lateral Ditch around the <br />active mine area east of 27 Rd <br />2002 <br />3 <br />Installed a portion of the 26" HDPE pipe into its permanent location in <br />Section 1-( west of 27 Rd to end of pipeline- Morgan field) <br />2003 <br />4 <br />Construct BB 27 Detour Rd to Morgan, Enstrom, Johnson, Wilcox <br />2003 <br />5 <br />Extended the temporary 12" HDPE pipeline further into Section 36 to <br />service James Johnson <br />2006 <br />6 <br />Abandon the temporary 12" HDPE pipeline to Johnson property. No <br />longer needed since WFC exercised its lease agreement. <br />2007 <br />7 <br />Bury the 26 " & 12" HDPE pipeline into its permanent location in <br />Section 31 and connect it to the already permeant 26" pipe in Section 1 <br />to completely finish the entire pipeline project. <br />2007 <br />8 <br />Finish building 27 & BB East Rd to final graveled grade. The road was <br />opened for Public use and BB Detour Rd was closed. Pavement still <br />needs to be completed for project is finalized. <br />2008 <br />9 <br />Pave 27 Road and BB Road in original locations and restore Sunshine <br />Ranch Corner intersection. <br />2010 <br />10 <br />Remove BB Road detour and reclaim road area <br />2009 <br />11 <br />Mine west to last cut at western permit boundary <br />2013 <br />12 <br />Backfill final cut with overburden stockpile <br />2015 <br />13 <br />Retopsoil and revegetate final cut area <br />2016 <br />14 <br />Replace BB Road from Sunshine Ranch Corner to western boundary. <br />2015 <br />15 <br />Continue to irrigate and monitor reclaimed areas until final bond release. <br />2015 -Bond <br />Release <br />Page 2.05.3(3)-39 October 2015 (TR -69) <br />