Exhibit D- Extraction Plan <br />might not otherwise be reclaimed. Essentially, since Tracts A and B are void of soil, <br />Tract B will be extracted first while plant operations are established over Tract A. <br />Extraction will then follow over Tracts C, D, and A. Simultaneous extraction with Tract <br />B in other Tracts may occur by simply providing additional warranty for Standard <br />Extraction Fronts, as previously described above and detailed under Exhibit L — <br />Reclamation Costs. <br />Set up of Plant operations and on -set of extraction activities in Tracts A and B, <br />respectively, will better allow for the use of over the shoulder removal of soil from <br />Tracts C and D to effect the reclamation of the designated affected lands in Tracts A <br />and B. The timetable for extraction, commencing approximately fall to winter 2010; is <br />estimated to take 20± years combined followed by an additional five years to complete <br />reclamation; or a total estimated life of the mine of 25± years; ending approximately <br />winter 2035-36. <br />Varra Companies, Inc. Permit M-2010-049 6 <br />Western Sugar Reclamation Land Development Project OMLR 112 Permit Amendment 2015 <br />