Laserfiche WebLink
2) No COE Permit is needed since no activity will take place near a water of the United States. <br />3) No NPDES permit will be needed for the site since the entire runoff for the 100 year 24 hour <br />event will be contained. <br />4) No Gravel Well permit is needed from the Division of Water Resources since no water will be <br />encountered in the extraction. <br />5) A fugitive emissions permit is needed for the extraction and processing since the permitted <br />production could exceed 80,000 tons per year. The portable crusher/screen plant, the concrete <br />batch plant and the portable asphalt plant will have their own emissions permits. <br />6) A spill and containment plan will be made although oils and grease will not be stored on site. <br />Each plant on site will have a double walled fuel tank for secondary containment. <br />7) No stormwater management plan is needed since the site will contain the 100 year 24 hour <br />runoff. <br />Berry Pit 3/02 31 <br />