CRIPPLE CREEK & VICTOR GOLD MINING Co. <br /> ANGLOGOLD ASHANTI (COLORADO) amec <br /> SQUAW GULCH (VLF) WEEKLY REPORT foster <br /> wheeler <br /> See attached figure for approved subgrade. <br /> Soil Liner Fill: <br /> A Cat smooth drum roller, a Cat excavator and a water truck conditioned and compacted SLF <br /> prior to geomembrane deployment. <br /> Two Cat smooth drum rollers (connected by cable to thrust block) and a Cat excavator with a <br /> smooth drum roller attachment compacted SLF below stations HM15+00 to HM20+00. <br /> Two Cat smooth drum rollers (connected by cable to thrust block) and a Cat excavator with a <br /> smooth drum roller attachment compacted SLF below stations HM8+00 to HM18+00. Cat 740 <br /> haul trucks transported SLF to stations FM6+00 to FM8+00. A Cat dozer continued building an <br /> SLF road above the FM Bench. Cat dozers placed SLF above stations FM6+00 to FM12+00. <br /> John Deere 740 haul trucks delivered SLF to station F8+00. Cat dozers continued building an <br /> SLF road across the F Bench between stations F8+00 to F10+00. <br /> Cameron SLF processing continued. <br /> All of the above Soil Liner Fill material was placed, graded, and compacted per the project plans <br /> and specifications. Moisture content, density testing and depth verification were performed per <br /> project specification prior to surface acceptance and geomembrane installation. <br /> See attached figure for approved SLF. <br /> Drain Cover Fill: <br /> Cat 740 haul trucks transported DCF from the stockpile to Phase 1. Low ground pressure Cat <br /> dozers placed DCF on approved geomembrane in Phase 1. <br /> See attached figure for approved DCF. <br /> Spent Ore Fill: <br /> A Cat D9 dozer continued placement of Spent Ore to engulf the open water in the PSSA prior to <br /> scheduled loading of Crushed Ore in the Fourth Quarter 2015. <br /> Underdrain System: <br /> Primary Underdrain: Complete. <br /> Secondary Underdrain: None. <br /> Tertiary Underdrain: None. <br /> Leak Detection: <br /> A Cat excavator prepared Leak Detection trench between stations F10+00 to F11+50. A Cat <br /> skidsteer assisted with construction of approximately 150 LF of Leak Detection. Construction and <br /> backfill was performed per project plans and specifications. <br /> Miscellaneous: <br /> Amec personnel continued LVSCS pump monitoring and observation. <br />