<br />Associatesw Technical Memorandum
<br />Notes:
<br />Holes are listed in the order grouted
<br />ft bgs = feet below ground surface
<br />ft ags = feet above ground surface
<br />3.4 Daily Site Activities
<br />Hayward Baker mobilized to the site on Tuesday, June 2, 2015. Whetstone arrived on site on June 3,
<br />2015 and Hayward Baker finished setting up their equipment and began drilling.
<br />On June 3, 2015 through June 9, 2015 Hayward Baker installed collars to the top of bedrock for the
<br />planned 14 primary and 13 secondary holes (Table 2). Collars for the first few holes (FI - S4 and
<br />F9) were drilled with a seven-inch bit and completed with four -inch schedule 40 PVC grouted into
<br />place. Collars F5 - S8 and S9 - F14 were drilled with a five -inch bit and completed with three-inch
<br />schedule 40 PVC grouted into place. Because a tagging probe was dropped down F3 on June 12,
<br />2015 before it was completed, a new collar (F3B) had to be installed on June 15, 2015. The collar
<br />for F15 was installed on June 22, 2015, F16 on June 23, 2015, and F17 on June 26, 2015 (Table 1).
<br />The collars for F3B, F15, F16, and F17 were all drilled with a five -inch bit and completed with 3 -
<br />inch schedule 40 PVC grouted into place.
<br />On June 5, 2015 Hayward Baker began drilling primary holes to TD. Primary boreholes were drilled
<br />vertically to approximately 40' below the top of bedrock using a 2.5 -inch bit. The original 14
<br />primary boreholes were completed by June 16, 2015. F 15 and F 16 were completed on June 25, 2015
<br />and F 17 was completed on June 29, 2015 (Table 2).
<br />On June 6, 2015 Hayward Baker began performing pressure tests on primary boreholes to evaluate
<br />permeability prior to grouting (Table 3). For the first 13 holes tested, pressure tests were conducted
<br />on 10 foot intervals over the length of the entire borehole. For the subsequent holes, pressure tests
<br />were performed in a single stage on the entire borehole. If the entire length of the borehole exceeded
<br />the limits of the equipment, pressure tests were performed on the bottom half of the borehole. If the
<br />bottom half of the borehole exceeded the limits of the equipment, pressure tests were conducted on
<br />10 foot intervals over the length of the entire borehole. Pressure tests on the original 14 primary
<br />4109C.150730 12
<br />Stage
<br />Avg.
<br />Total
<br />Hole
<br />Stage
<br />Date
<br />Duration
<br />Top
<br />Bottom
<br />Length
<br />Refusal
<br />Volume
<br />Number
<br />Number
<br />(min)
<br />(ft bgs)
<br />(ft bgs)
<br />(ft)
<br />Pressure
<br />(gal)
<br />(bar)
<br />S13
<br />3
<br />6/26/2015
<br />1.07
<br />30
<br />40
<br />10
<br />1.5
<br />0.31
<br />S13
<br />2
<br />6/26/2015
<br />1.12
<br />20
<br />30
<br />10
<br />1.11
<br />0.24
<br />S13
<br />2
<br />6/26/2015
<br />1.15
<br />9.5
<br />19.5
<br />10
<br />0.78
<br />0.17
<br />S4
<br />3
<br />6/26/2015
<br />1.95
<br />25
<br />35
<br />10
<br />1.6
<br />0.87
<br />S4
<br />2
<br />6/26/2015
<br />1.98
<br />15
<br />25
<br />10
<br />1.09
<br />0.46
<br />S4
<br />1
<br />6/26/2015
<br />56.63
<br />5.6
<br />14.85
<br />9.25
<br />0.35
<br />103.59
<br />S4
<br />1
<br />6/29/2015
<br />37.08
<br />5.7
<br />15.7
<br />10
<br />0.72
<br />137.42
<br />S8
<br />4
<br />6/30/2015
<br />159.38
<br />40
<br />46.4
<br />6.4
<br />1.04
<br />579.84
<br />S5
<br />4
<br />6/30/2015
<br />1.98
<br />37
<br />47
<br />10
<br />0.63
<br />2.83
<br />S5
<br />3
<br />6/30/2015
<br />65.02
<br />27
<br />37
<br />10
<br />2
<br />78.83
<br />S5
<br />2
<br />6/30/2015
<br />8.82
<br />17
<br />27
<br />10
<br />1.65
<br />4.01
<br />S5
<br />1
<br />6/30/2015
<br />0.38
<br />7
<br />17
<br />10
<br />0.52
<br />0.77
<br />Notes:
<br />Holes are listed in the order grouted
<br />ft bgs = feet below ground surface
<br />ft ags = feet above ground surface
<br />3.4 Daily Site Activities
<br />Hayward Baker mobilized to the site on Tuesday, June 2, 2015. Whetstone arrived on site on June 3,
<br />2015 and Hayward Baker finished setting up their equipment and began drilling.
<br />On June 3, 2015 through June 9, 2015 Hayward Baker installed collars to the top of bedrock for the
<br />planned 14 primary and 13 secondary holes (Table 2). Collars for the first few holes (FI - S4 and
<br />F9) were drilled with a seven-inch bit and completed with four -inch schedule 40 PVC grouted into
<br />place. Collars F5 - S8 and S9 - F14 were drilled with a five -inch bit and completed with three-inch
<br />schedule 40 PVC grouted into place. Because a tagging probe was dropped down F3 on June 12,
<br />2015 before it was completed, a new collar (F3B) had to be installed on June 15, 2015. The collar
<br />for F15 was installed on June 22, 2015, F16 on June 23, 2015, and F17 on June 26, 2015 (Table 1).
<br />The collars for F3B, F15, F16, and F17 were all drilled with a five -inch bit and completed with 3 -
<br />inch schedule 40 PVC grouted into place.
<br />On June 5, 2015 Hayward Baker began drilling primary holes to TD. Primary boreholes were drilled
<br />vertically to approximately 40' below the top of bedrock using a 2.5 -inch bit. The original 14
<br />primary boreholes were completed by June 16, 2015. F 15 and F 16 were completed on June 25, 2015
<br />and F 17 was completed on June 29, 2015 (Table 2).
<br />On June 6, 2015 Hayward Baker began performing pressure tests on primary boreholes to evaluate
<br />permeability prior to grouting (Table 3). For the first 13 holes tested, pressure tests were conducted
<br />on 10 foot intervals over the length of the entire borehole. For the subsequent holes, pressure tests
<br />were performed in a single stage on the entire borehole. If the entire length of the borehole exceeded
<br />the limits of the equipment, pressure tests were performed on the bottom half of the borehole. If the
<br />bottom half of the borehole exceeded the limits of the equipment, pressure tests were conducted on
<br />10 foot intervals over the length of the entire borehole. Pressure tests on the original 14 primary
<br />4109C.150730 12