Laserfiche WebLink
Whetstone <br />,j <br />Associatesw Technical Memorandum <br />Notes: <br />Holes are listed in the order grouted <br />ft bgs = feet below ground surface <br />ft ags = feet above ground surface <br />3.4 Daily Site Activities <br />Hayward Baker mobilized to the site on Tuesday, June 2, 2015. Whetstone arrived on site on June 3, <br />2015 and Hayward Baker finished setting up their equipment and began drilling. <br />On June 3, 2015 through June 9, 2015 Hayward Baker installed collars to the top of bedrock for the <br />planned 14 primary and 13 secondary holes (Table 2). Collars for the first few holes (FI - S4 and <br />F9) were drilled with a seven-inch bit and completed with four -inch schedule 40 PVC grouted into <br />place. Collars F5 - S8 and S9 - F14 were drilled with a five -inch bit and completed with three-inch <br />schedule 40 PVC grouted into place. Because a tagging probe was dropped down F3 on June 12, <br />2015 before it was completed, a new collar (F3B) had to be installed on June 15, 2015. The collar <br />for F15 was installed on June 22, 2015, F16 on June 23, 2015, and F17 on June 26, 2015 (Table 1). <br />The collars for F3B, F15, F16, and F17 were all drilled with a five -inch bit and completed with 3 - <br />inch schedule 40 PVC grouted into place. <br />On June 5, 2015 Hayward Baker began drilling primary holes to TD. Primary boreholes were drilled <br />vertically to approximately 40' below the top of bedrock using a 2.5 -inch bit. The original 14 <br />primary boreholes were completed by June 16, 2015. F 15 and F 16 were completed on June 25, 2015 <br />and F 17 was completed on June 29, 2015 (Table 2). <br />On June 6, 2015 Hayward Baker began performing pressure tests on primary boreholes to evaluate <br />permeability prior to grouting (Table 3). For the first 13 holes tested, pressure tests were conducted <br />on 10 foot intervals over the length of the entire borehole. For the subsequent holes, pressure tests <br />were performed in a single stage on the entire borehole. If the entire length of the borehole exceeded <br />the limits of the equipment, pressure tests were performed on the bottom half of the borehole. If the <br />bottom half of the borehole exceeded the limits of the equipment, pressure tests were conducted on <br />10 foot intervals over the length of the entire borehole. Pressure tests on the original 14 primary <br />4109C.150730 12 <br />Stage <br />Avg. <br />Total <br />Hole <br />Stage <br />Date <br />Duration <br />Top <br />Bottom <br />Length <br />Refusal <br />Volume <br />Number <br />Number <br />(min) <br />(ft bgs) <br />(ft bgs) <br />(ft) <br />Pressure <br />(gal) <br />(bar) <br />S13 <br />3 <br />6/26/2015 <br />1.07 <br />30 <br />40 <br />10 <br />1.5 <br />0.31 <br />S13 <br />2 <br />6/26/2015 <br />1.12 <br />20 <br />30 <br />10 <br />1.11 <br />0.24 <br />S13 <br />2 <br />6/26/2015 <br />1.15 <br />9.5 <br />19.5 <br />10 <br />0.78 <br />0.17 <br />S4 <br />3 <br />6/26/2015 <br />1.95 <br />25 <br />35 <br />10 <br />1.6 <br />0.87 <br />S4 <br />2 <br />6/26/2015 <br />1.98 <br />15 <br />25 <br />10 <br />1.09 <br />0.46 <br />S4 <br />1 <br />6/26/2015 <br />56.63 <br />5.6 <br />14.85 <br />9.25 <br />0.35 <br />103.59 <br />S4 <br />1 <br />6/29/2015 <br />37.08 <br />5.7 <br />15.7 <br />10 <br />0.72 <br />137.42 <br />S8 <br />4 <br />6/30/2015 <br />159.38 <br />40 <br />46.4 <br />6.4 <br />1.04 <br />579.84 <br />S5 <br />4 <br />6/30/2015 <br />1.98 <br />37 <br />47 <br />10 <br />0.63 <br />2.83 <br />S5 <br />3 <br />6/30/2015 <br />65.02 <br />27 <br />37 <br />10 <br />2 <br />78.83 <br />S5 <br />2 <br />6/30/2015 <br />8.82 <br />17 <br />27 <br />10 <br />1.65 <br />4.01 <br />S5 <br />1 <br />6/30/2015 <br />0.38 <br />7 <br />17 <br />10 <br />0.52 <br />0.77 <br />Notes: <br />Holes are listed in the order grouted <br />ft bgs = feet below ground surface <br />ft ags = feet above ground surface <br />3.4 Daily Site Activities <br />Hayward Baker mobilized to the site on Tuesday, June 2, 2015. Whetstone arrived on site on June 3, <br />2015 and Hayward Baker finished setting up their equipment and began drilling. <br />On June 3, 2015 through June 9, 2015 Hayward Baker installed collars to the top of bedrock for the <br />planned 14 primary and 13 secondary holes (Table 2). Collars for the first few holes (FI - S4 and <br />F9) were drilled with a seven-inch bit and completed with four -inch schedule 40 PVC grouted into <br />place. Collars F5 - S8 and S9 - F14 were drilled with a five -inch bit and completed with three-inch <br />schedule 40 PVC grouted into place. Because a tagging probe was dropped down F3 on June 12, <br />2015 before it was completed, a new collar (F3B) had to be installed on June 15, 2015. The collar <br />for F15 was installed on June 22, 2015, F16 on June 23, 2015, and F17 on June 26, 2015 (Table 1). <br />The collars for F3B, F15, F16, and F17 were all drilled with a five -inch bit and completed with 3 - <br />inch schedule 40 PVC grouted into place. <br />On June 5, 2015 Hayward Baker began drilling primary holes to TD. Primary boreholes were drilled <br />vertically to approximately 40' below the top of bedrock using a 2.5 -inch bit. The original 14 <br />primary boreholes were completed by June 16, 2015. F 15 and F 16 were completed on June 25, 2015 <br />and F 17 was completed on June 29, 2015 (Table 2). <br />On June 6, 2015 Hayward Baker began performing pressure tests on primary boreholes to evaluate <br />permeability prior to grouting (Table 3). For the first 13 holes tested, pressure tests were conducted <br />on 10 foot intervals over the length of the entire borehole. For the subsequent holes, pressure tests <br />were performed in a single stage on the entire borehole. If the entire length of the borehole exceeded <br />the limits of the equipment, pressure tests were performed on the bottom half of the borehole. If the <br />bottom half of the borehole exceeded the limits of the equipment, pressure tests were conducted on <br />10 foot intervals over the length of the entire borehole. Pressure tests on the original 14 primary <br />4109C.150730 12 <br />