Exhibit D- Mining Plan <br />highest possible end-use. End use may vary over the reclaimed lands and will <br />comprise a variety of mixed uses. Mixed use may include other agricultural uses; <br />as well as light residential, commercial, or industrial uses. <br />While the on -set of reclamation is concurrent with extraction, the completion of <br />reclamation may lag up to five (5.0±) years behind the onset of reclamation <br />activities. Complete extraction of the permit area is expected to take <br />approximately 25-30 years, depending upon market conditions, with an additional <br />5 years following completion of all extraction activities for ultimate completion of <br />concurrent reclamation activities, placing the completion of all activities near <br />2045-2050, depending upon the date of start-up. <br />Varra Companies, Inc. OMLR 112 Permit Application 7 <br />Parcel 122 — Resource Development Project 1 July 2015