June 30, 2015 <br />Photograph 2: North Site above the 7350 Bench Elevation (6/25/2015) <br />Photograph 3: Spring above the 7470 Bench Elevation (6/25/2015) <br />2.0 Critical Construction Periods <br />2.1 Removal of All Organic Material and Topsoil <br />Topsoil and organic material removal activities were not conducted during the quarter. <br />2.2 Placement of Underdrainage Systems <br />The underdrainage system was completed in the first quarter of 2010; additional work on this <br />system is not anticipated. During the time of the inspection, there was less than half of a gallon <br />per minute of water flow. <br />3 <br />