Exhibit L— Reclamation Costs <br /> The maximum affected area is approximately 1.5 acres inside the boundary and <br /> 0.23 (not including the road) outside the boundary. For a total of 1.73 acres that <br /> will require reclamation. The reclamation would be accomplished in one phase. <br /> We anticipate being able to stockpile the existing soil but for this cost estimate we <br /> are assuming topsoil will be purchased. The affected area will be on the same <br /> slopes and configuration as the existing topography. Therefore we anticipate <br /> minimal re-grading. The costs are summarized as follows: <br /> Seeding, 1.73 acres @ $2,500/acre $4,325 <br /> Weed control $2,000 <br /> Topsoil, 3,190 cy @ $1.80/cy $5,740 <br /> Minimal re-grading $3,000 <br /> Total Reclamation $15,065 <br /> Table 2 shows the preliminary estimate to construct the french drain and pipeline. <br /> The total cost is as follows: <br /> Total Reclamation $31,440 <br /> French Drain and pipe $147,500 <br /> Total Cost $178,940 <br />