For temporary construction disturbance, the effective disturbance area will be minimized to the extent
<br />reasonably feasible, and the affected stream channel, banks, and any affected floodplain areas will be restored to
<br />their original configuration through backf lling, compaction, grading, and placement of armoring (as
<br />appropriate). Disturbance areas will be reseeded with TC's standard riparian seed mix.
<br />For long -term road or railroad crossings, culverts or other appropriate designed flow structures will be installed
<br />to safely pass the design flows in compliance with applicable provisions of Rule 4.03, and inlets will be armored
<br />to protect against erosion. If the road /railroad is approved as a permanent postmining feature, the associated
<br />drainage structures will remain in place. If the road/railroad crossing is to be removed as a part of mine
<br />reclamation, the affected stream channel, banks, and floodplain areas will be restored at that time, as previously
<br />described.
<br />Impacts of Mine Water DischarLye
<br />The relatively continuous discharge of mine water to Foidel Creek constitutes a significant proportion of total
<br />streamflow during low flow periods. This will result in perennial flow in Foidel Creek, while the mine is
<br />discharging to Foidel Creek. When the Fish Creek dewatering site is operating (typically limited to the spring
<br />and early summer runoff period), it can represent a significant portion of the Fish Creek flow. Runoff flows in
<br />Foidel Creek should increase during the period when the mine is discharging. Projected mine inflows through
<br />the life of the mine have been re- estimated based on current data and are discussed in the Ground Water PHC
<br />section, Ground Water Inflow to the Mine. The maximum discharge to Foidel Creek from Pond D and the TORT
<br />Boreholes is expected to be approximately 1,200 gpm on a temporary basis, and approximately 400 -600 gpm on
<br />an average annual basis. Maximum discharge from the Fish Creek Boreholes and Site 115 will range up to
<br />1,200 gpm, however, average annual discharges will range from 55 to 300 gpm (due to seasonal limitations).
<br />Mine Discharees
<br />The 1998 inflows and the estimated future mine inflows are shown in Exhibit 51, Table E514. Projected mine
<br />discharges are shown on Exhibit 51, Tables E51 -6 through E51 -8. The mining rate used in these projections
<br />was 8,000,000 tons per year. An increased mining rate will not affect the maximum flow rates, but only move
<br />them forward in time. The mine groundwater inflow numbers are discussed above in the Ground Water Inflow
<br />to the Mine section.
<br />Mine inflows will be discharged through the Fish Creek and 10 -Right boreholes. During periods when these
<br />pumps are not operating the sumps below the boreholes fill with mine inflow water. The (1998/1999) Fish
<br />Creek pool volume was estimated to be 546,000,000 gallons (1675 acre -ft, Ground Water Inflow to the Mine,
<br />Mine Water Balance). When both pumps at either the Fish Creek or 10 -Right boreholes are running they are
<br />capable of discharging at approximately 1,000 gpm, although this rate may be increased to 1,200 gpm if
<br />warranted. The annual average pumping rate is estimated to be 300 gpm for the Fish Creek installation and 400-
<br />600 for the 10 -Right installation. Operationally, pumping rates will be maintained at levels sufficient to keep
<br />the underground water storage reservoirs below the target freeboard elevations relative to the mine seals.
<br />Tn June 1999, a system to recycle some of the water that is produced underground was completed. This system
<br />could recycle over 175 gpm, with an average annual recycling rate conservatively estimated at 100 gpm. The
<br />system was designed to allow for the addition of some makeup water, if needed to dilute any salt build -up.
<br />However, it did not lake into account that additional water could be used to replace surface uses of water such as in
<br />the truck -wash, road watering, and the preparation plant, further decreasing the water discharged fronn Site 109.
<br />Three cases are presented. In Case I (Exhibit 51, Table E51 -6) all the water is pumped from Site 109 except the
<br />WMD inflow to the Fish Creek Borehole sump. In Case 2 (Exhibit 51, Table E51 -7), after the water level in the
<br />sump is lowered, 245 gpm of water is transferred into the sump from the eastern and northern parts of the mine. In
<br />Case 3 (Exhibit 51, Table E51 -8), water is continuously diverted into the sump, and the discharge rate from Site 1
<br />15 increased, to compensate for the diversion.
<br />The average water duality discharged from the Site 115 was estimated by incrementally averaging the average
<br />conductivity in the water in storage with the estimated conductivity of the WMD ground water inflow
<br />TR13 -83 2.05 -151 11 /03 /14
<br />
|