DIVISION 1- GENERAL REQUIREMENTS <br />SECTION 01700 - CONTRACT CLOSEOUT <br />1.01 CLOSEOUT PROCEDURES <br />The following project closeout procedure defines the responsibilities of the Contractor, Owner and <br />Engineer in closing the project: <br />Step 1: Contractor advises the Engineer in writing that he has reached "Substantial Completion" and <br />provides a list of items to be completed or corrected. <br />Closeout may be conducted by areas or portions of the work if requested by the Owner. <br />Step 2: Engineer observes the work to determine if it is substantially complete, and issues a "Punch List" <br />of items to be completed or corrected. <br />Step 3: Contractor completes and/or corrects all punch list items and notifies the Engineer in writing that <br />his work is ready for final inspection. <br />Step 4: Engineer makes final examination. When the work is found to be acceptable, the Contractor will <br />prepare a final construction report and as-built plans. <br />END OF SECTION <br />Wattenberg Resource Pond 3 Slurry Wall Section 01700 — Contract Closeout <br />Page 1 <br />