Laserfiche WebLink
DIVISION 1- GENERAL REQUIREMENTS <br />SECTION 01330 - SURVEY DATA <br />1.01 SURVEY REQUIREMENTS <br />A. Construction Stakeout: <br />Owner will provide initial slurry wall alignment staking. <br />2. Engineer has established all temporary benchmarks as found on the Drawings. Base all <br />vertical measurements on established control. <br />3. Stake the slurry trench along its alignment at all beginning and ends of all curves and at <br />50 -foot stations. <br />B. All survey data developed by Contractor in performing surveys required by the Work will be <br />available to the Engineer for examination throughout the construction period. <br />C. Contractor shall mark the as- constructed slurry wall alignment with stakes above the slurry wall <br />centerline set at 100 -foot spacing. <br />1.02 SUBMITTALS <br />Notify Engineer of proposed changes in the alignment for approval a minimum of 48 hours prior to <br />adjusting alignment. <br />END OF SECTION <br />Wattenberg Resource Pond 3 Slurry Wall Section 01330 — Survey Data <br />Page 1 <br />