DIVISION 1- GENERAL REQUIREMENTS <br />SECTION 01310 - CONSTRUCTION SCHEDULES <br />1.01 GENERAL <br />A. Prepare detailed schedule of all construction operations and procurement to be reviewed by the <br />Engineer prior to commencing construction. <br />No work is to begin at the site until Engineer's acceptance of the Construction Progress Schedule <br />and Report of delivery of equipment and materials. <br />1.02 FORMAT AND SUBMISSIONS <br />A. Prepare construction and procurement schedules in a graphic format suitable for displaying <br />schedule and actual progress. <br />B. Submit two copies of each schedule to the Engineer for review. <br />The Engineer will return one copy to the Contractor with revisions suggested or necessary for <br />coordination of the Work with the needs of the Engineer or others. <br />1.03 CONTENT <br />A. Construction Progress Schedule <br />1. Show the complete Work sequence of construction by activity and location. <br />2. Show the dates for the beginning and completion of: <br />a. Slurry wall construction in maximum 10 working day increments. <br />b. Earthwork operations. <br />C. Testing. <br />3. Show projected percentage of completion for each item as of the first day of the month. <br />B. Report of delivery of equipment and materials <br />1. Show delivery status of critical and major items of equipment and materials. <br />2. Include a schedule which includes the critical path for Shop Drawings, tests, and other <br />submittal requirements for equipment and materials. <br />1.04 PROGRESS REVISIONS <br />A. Submit revised schedules and reports when changes are foreseen or when required by the <br />Engineer. <br />B. Show changes occurring since previous submission. <br />1. Actual progress of each item to date. <br />2. Revised projections of progress and completion. <br />C. Provide a narrative report as needed to define: <br />Wattenberg Resource Pond 3 Slurry Wall Section 01310 — Construction Schedules <br />Page 1 <br />