Exhibit L <br /> Reclamation Costs <br /> Phase I: 15 acres disturbance with 2 acres of slope. There will be approximately 2,000 lineal <br /> feet of 2H:1 V slope at 15' height. This will require pushing down 8.333 cubic yards of material <br /> to achieve a 3H:1 V slope. <br /> Finish Grade 18.5 Hours @ $500.00/hour $ 9,250.00 <br /> Rip Pit Floor 22.5 Hours @ $370.00/hour $ 8,325.00 <br /> Spread Topsoil 22.5 Hours @ $500.00/hour $11,250.00 <br /> Vegetate 17 Acres @ $1,400.00/acre $23,800.00 <br /> Mobilize Crew 2 Hours @ $2,500.00/hour $ 5,000.00 <br /> TOTAL $57.625.00 <br /> Phase II: Same area as Phase I with the same costs. <br /> Phase III: 30 acres disturbance with 2 acres of slope not reclaimed and 4 acres reclaimed. <br /> Finish Grade 18.5 Hours @ $500.00/hour $ 9,250.00 <br /> Rip Pit Floor 45 Hours @ $370.00/hour $16,650.00 <br /> Spread Topsoil 45 Hours @ $500.00/hour $22,500.00 <br /> Vegetate 32 Acres @ $1,400.00/acre $44,800.00 <br /> Mobilize Crew 2 Hours @ $2,500.00/hour $ 5,000.00 <br /> TOTAL $98,200.00 <br /> Phase IV: Same area as Phase III with the same costs. <br /> Phase IV: 45 acres disturbance with 4 acres of slope not reclaimed and 8 acres reclaimed. <br /> Finish Grade 18.5 Hours @ $500.00/hour $ 9,250.00 <br /> Rip Pit Floor 67.5 Hours @ $370.00/hour $24,975.00 <br /> Spread Topsoil 67.5 Hours @ $500.00/hour $33,750.00 <br /> Vegetate 49 Acres @ $1,400.00/acre $68,600.00 <br /> Mobilize Crew 2 Hours @ $2,500.00/hour $ 5,000.00 <br /> TOTAL $141,575.00 <br /> L-1 <br />