Laserfiche WebLink
GP Aggregates LLC <br /> J&T Consulting, Inc. <br /> West Farm Pit <br /> 8/15/2014 <br /> !IIIIIIReclaillimati!li Bond Quantities and Costs <br /> 14 j&T Consulting,Inc. <br /> Phase 4(9.60 acres) <br /> 'Reclamation Operation Quantity Unit Unit Cost Cost I <br /> Active Mining Area <br /> Credit 20%Cost of Slurry Wall Required to Close Phase 3(70'avg Depth) (5,448) If $ 46 $ (250,608) <br /> Credit for Topsoil Area Above Water Required for Phases 1-3 (4.9) ac $ 2,000 $ (9,815) <br /> Credit for Revegetated Area Above Water Required for Phases 1-3 (4.9) ac $ 1,000 $ (4,907) <br /> Credit for Scarifying Ground in Disturbed Area Phase 4(Surface Area) (9.6) ac $ 200 $ (1,920) <br /> Credit for Topsoil Placement in Disturbed Area Phase 4(Surface Area) (9.6) ac $ 2,000 $ (19,200) <br /> Credit for Revegetate Disturbed Area Phase 4(Surface Area) (9.6) ac $ 1,000 $ (9,600) <br /> 20%Cost of Slurry Wall Required to Close Phase 4(70'avg Depth) 5,448 If $ 46 $ 250,608 <br /> Topsoil Area Above Water Required for Phases 1-4 5.0 ac $ 2,000 $ 10,017 <br /> Revegetate Area Above Water Required for Phases 1-4 5.0 ac $ 1,000 $ 5,008 <br /> Mobilization 1.00 Is $ 2,500 $ 2,500 <br /> Total Direct Cost $ (27,917) <br /> Overhead and Profit Cost(12.60%) $ (3,518) <br /> Contract Cost $ (31,435) <br /> Project Management(9.25%) $ (2,582) <br /> Additional Financial Warranty Required For Phase 4 $ (34,017)1 <br /> Phase 5(9.09 acres) <br /> 'Reclamation Operation Quantity Unit Unit Cost Cost I <br /> Active Mining Area <br /> Credit for Topsoil Area Above Water Required for Phases 1-4 (5.0) ac $ 2,000 $ (10,017) <br /> Credit for Revegetated Area Above Water Required for Phases 1-4 (5.0) ac $ 1,000 $ (5,008) <br /> 20%Cost of Slurry Wall Required to Close Phase 5(70'avg Depth) 2,239 If $ 46 $ 102,994 <br /> Topsoil Area Above Water Required for Phases 1-5 6.5 ac $ 2,000 $ 12,916 <br /> Revegetate Area Above Water Required for Phases 1-5 6.5 ac $ 1,000 $ 6,458 <br /> Mobilization 1.00 Is $ 2,500 $ 2,500 <br /> Total Direct Cost $ 109,844 <br /> Overhead and Profit Cost(12.60%) $ 13,840 <br /> Contract Cost $ 123,684 <br /> Project Management(9.25%) $ 10,161 <br /> 'Additional Financial Warranty Required For Phase 5 $ 133,845 I <br /> Phase 6(9.51 acres) <br /> 'Reclamation Operation Quantity Unit Unit Cost Cost I <br /> Active Mining Area <br /> Credit 20%Cost of Slurry Wall Required to Close Phase 5(70'avg Depth) (2,239) If $ 46 $ (102,994) <br /> Credit for Topsoil Area Above Water Required for Phases 1-5 (6.5) ac $ 2,000 $ (12,916) <br /> Credit for Revegetated Area Above Water Required for Phases 1-5 (6.5) ac $ 1,000 $ (6,458) <br /> 20%Cost of Slurry Wall Required to Close Phases 5-6(70'avg Depth) 2,724 If $ 46 $ 125,304 <br /> Topsoil Area Above Water Required for Phases 1-6 6.5 ac $ 2,000 $ 12,902 <br /> Revegetate Area Above Water Required for Phases 1-6 6.5 ac $ 1,000 $ 6,451 <br /> Mobilization 1.00 Is $ 2,500 $ 2,500 <br /> Total Direct Cost $ 24,788 <br /> Overhead and Profit Cost(12.60%) $ 3,123 <br /> Contract Cost $ 27,911 <br /> Project Management(9.25%) $ 2,293 <br /> 'Additional Financial Warranty Required For Phase 6 $ 30,204 I <br /> 3 of 7 <br />