Laserfiche WebLink
A Cat 312 excavator hammered oversized rock on the upslope of STA B4 +00 in the PSSA. <br />Cat dozers were finish grading and a Cat smooth drum roller compacted subgrade in various <br />areas within PSSA and surrounding Phase 1 slopes. <br />John Deere and Cat dozers were cutting material and slope contouring the area around the <br />Anaconda Mine Complex. <br />Subgrade: <br />The following subgrade areas in the PSSA were compacted per project specification to finished <br />grade, inspected and certified for soil liner fill (SLF) placement: <br />The north edge of roadway from STA 0 +00 to 8 +00 of the ADR haul road and down to <br />the PSSA floor. <br />The south edge of roadway from STA 0 +00 to 5 +00 of the ADR haul road. <br />See the attached subgrade acceptance map for all accepted subgrade locations. <br />Soil Liner Fill (SLF): <br />SLF was placed and compacted per project specification, then, inspected, tested and certified in <br />compliance with technical specifications in the following areas: <br />From STA 0 +00 to 5 +00 of the south edge of roadway of the ADR haul road and upslope <br />to Bench B floor. <br />From STA A10 +00 to Al2 +00 and downslope to the PSSA floor. <br />Between STA FFO +00 to FF2 +00 and DD4 +00 to DD6 +00 (Phase 1). <br />See the attached SLF acceptance map for all accepted locations. <br />SLF from the Squaw Gulch stockpile was hauled to northern and southern inboard slopes and to <br />the PSSA floor. The material was placed on the approved slope subgrade as fill and also <br />stockpiled on the PSSA floor for later use in the area. <br />SLF was placed in a loose lift approximately 1.5 feet thick on the approved subgrade by Cat GPS <br />dozers and 740 Haul Trucks. <br />SLF finishing and contouring occurred on the SLF at the PSSA North and South slopes. <br />Density tests, N -80 to N -96, and depth checks, D -48 to D -54, were performed. <br />Record Sample, SLF -16 -R, was collected and returned to AMEC's laboratory for analysis. <br />SLF Processina: <br />Cameron Site: No soil liner fill mining or processing occurred at the Cameron Site. <br />Approximately 244,860 tons of SLF material has been produced and remains stockpiled at the <br />Cameron Site for future use. The soil liner fill processing equipment remains at the Cameron site. <br />No new processing during this reporting period. <br />Underdrain System: <br />Primary Underdrain: Complete. <br />Secondary Underdrain: No work was performed on the secondary underdrain. <br />Tertiary Underdrain: Complete in PSSA footprint. <br />2014.07.12 -mle2 weekly final Page 2 of 7 <br />