June 25, 2014 <br />2.0 Critical Construction Periods <br />2.1 Removal of All Organic Material and Topsoil <br />Topsoil and organic material removal activities were not conducted during the quarter. <br />2.2 Placement of Underdrainage Systems <br />The underdrainage system was completed in the first quarter of 2010; additional work on this system is <br />not anticipated. During the time of the inspection, there was approximately half a gallon per minute of <br />water flow. <br />2.3 Installation of Surface Drainage Systems <br />Both the north and south surface drains were inspected (Photographs 2 and 3). At the time of <br />inspection there were no signs of water flow. The upper drain was inspected and was in excellent <br />condition (Photograph 4). <br />Photograph 2: North Surface Drain Looking Northeast (612512014) <br />