Table 4: Reclamation Costs-Three Bells Reclamation <br /> Veldman Property Reclamation Costs <br /> Item Unit Quantityl Unit Price Extension <br /> 1 Mobilization/Demobilization LS 1 $ 5,000 $ 5,000 <br /> 2 Dewaterin LS 1 $ 18,333 $ 18,333 <br /> 3 Highwall Excavation and Roadway Fill LS 1 $ 83,333 $ 83,333 <br /> 4 Foundation Preparation and Cutoff Key Excavation CY 20,000 $ 3 $ 69,000 <br /> 5 Common Fill/Lot Fill CY 40,300 $ 3 $ 139,035 <br /> 6 Zone 151ope Liner Embankment Fill CY 243,600 $ 3 $ 840,420 <br /> 7 Reservoir Access Ramp LS 2 $ 4,000 $ 8,000 <br /> 8 Extend Existing Ditch LF 700 $ 2 $ 1,155 <br /> 9 Seepage Swale Construction LF 3,100 $ 2 $ 4,960 <br /> 10 Bedrock Over Excavation CY 5,000 $ 2 $ 7,500 <br /> 11 As-Constructed Information LS 1 $ 5,000 $ 5,000 <br /> 12 Topsoil Stripping and Stockpiling LS 1 $ 40,000 $ 40,000 <br /> 13 Revegetation AC 16 $ 200 $ 3,200 <br /> Total Reclamation Cost for Veldman $ 1,224,937 <br /> Total Reclamation Cost per acre(81 acres) $ 15 123 <br /> Ditullio Property Reclamation Costs <br /> Phase 1 <br /> 1 Mobilization/Demobilizaiton LS 1 $ 5,000 $ 5,000 <br /> 2 Dewaterin LS 1 $ 18,300 $ 18,300 <br /> 3 Highwall Excavation CY 2,000 $ 2 $ 4,000 <br /> 4 Foundation Preparation/Keyway Preparation LF 1,910 $ 5 $ 9,550 <br /> 7 Zone la Slope Liner CY 40,000 $ 4 $ 140,000 <br /> 8 Revegetation AC 1 $ 200 $ 196 <br /> Total Reclamation Cost for Ditullio-Phase 1 <br /> $ 177,046 <br /> Total Reclamation Cost per acre(6 acres) $ 29,508 <br /> Phase 3 <br /> 1 Mobilization/Demobilizaiton LS 1 $ 5,000 $ 5,000 <br /> 2 Dewatering LS 1 $ 18,300 $ 18,300 <br /> 3 Highwall Excavation CY 2,000 $ 2 $ 4,000 <br /> 4 Foundation Preparation/Keyway Preparation LF 4,680 $ 5 $ 23,400 <br /> 6 Roadway Fill CY 10,000 $ 4 $ 35,000 <br /> 7 Zone la Slope Liner CY 69,000 $ 4 $ 241,500 <br /> 8 Revegetation AC 3 $ 200 $ 572 <br /> Total Reclamation Cost for Ditullio-Phase 3 $ 327,772 <br /> Total Reclamation Cost per acre(17acres) $ 19,281 <br /> Phase 4 <br /> 1 Mobilization/Demobilizaiton LS 1 $ 5,000 $ 5,000 <br /> 2 Dewatering LS 1 $ 18,300 $ 18,300 <br /> 3 Highwall Excavation CY 2,000 $ 2 $ 4,000 <br /> 4 Foundation Preparation/Keyway Preparation LF 6,670 $ 5 $ 33,350 <br /> 5 Phase 4 Backfill CY 442,000 $ 2 $ 884,000 <br /> 7 Zone la Slope Liner CY 163,000 $ 4 $ 570,500 <br /> 8 Revegetation AC 10 $ 200 $ 22,052 <br /> Total Reclamation Cost for Ditullio-Phase 4 $ 1,537,202 <br /> Total Reclamation Cost per acre(70 acres) $ 21,960 <br /> Phase 2 and 5 Revegetation <br /> 1 Revegetation AC 22 $ 200 $ 22,052 <br /> Total Reclamation Cost for Ditullio-Phase 2 and 5 $ 22,052 <br /> Total Reclamation Cost per acre(22 acres) $ 1,002 <br /> GEI Consultants,Inc. 27 June 2014 <br /> Three Bells Mine Reclamation Permit Amendment <br />